docketrouter
Clause survey / Force majeure

Force majeure

22 states, 22 rules, 189 authorities. Each state's card gives the rule, the trap that makes a clause drafted elsewhere fail there, and every authority with the sentences that state the rule. A state not listed is one we do not answer this family for.

22 of 22 read at the 2026-10-03 bar. A rule read at an earlier bar is not a rule that passes this one, and each card says which it is.

  1. read at the 2026-10-03 bar

    Does Alabama excuse performance when the event the clause was meant to cover happens?

    For a sale of goods there is a statutory default; outside it an absolute promise must be kept unless the contract itself excused the event. Except so far as a seller may have assumed a greater obligation and subject to § 7-2-614 on substituted performance, delay in delivery or nondelivery in whole or in part by a seller who complies with paragraphs (b) and (c) is not a breach of his duty under a contract for sale if performance as agreed has been made impracticable by the occurrence of a contingency the nonoccurrence of which was a basic assumption on which the contract was made, or by compliance in good faith with any applicable foreign or domestic governmental regulation or order whether or not it later proves to be invalid (Ala. Code § 7-2-615(a)). A seller whose capacity is only partly affected must allocate production and deliveries among customers in any manner that is fair and reasonable, and must notify the buyer seasonably of the delay or nondelivery and of any quota (§ 7-2-615(b)-(c)). Where without fault of either party the agreed berthing, loading or unloading facilities fail, the agreed type of carrier becomes unavailable, or the agreed manner of delivery otherwise becomes commercially impracticable but a commercially reasonable substitute is available, that substitute performance must be tendered and accepted (§ 7-2-614(1)). On notice of a material or indefinite delay or an allocation, the buyer may, by written notification to the seller, terminate and thereby discharge any unexecuted portion of the contract or modify the contract by agreeing to take his available quota in substitution; if the buyer does not so modify within a reasonable time not exceeding 30 days the contract lapses as to the deliveries affected; and § 7-2-616's provisions may not be negated by agreement except insofar as the seller has assumed a greater obligation under § 7-2-615 (§ 7-2-616(1)-(3)). Outside a sale of goods the Supreme Court of Alabama holds a promisor strictly to the literal terms of his promise: where one by his contract undertakes an obligation which is absolute, he is bound to perform within the terms of the contract or answer in damages, despite an act of God, unexpected difficulty, or hardship, because these contingencies could have been provided against by his contract, so the contractor who could not obtain a material the specifications named lost its impossibility defence and the liquidated-damages assessment against it was affirmed (Alpine Construction Co. v. Water Works Board of the City of Birmingham, 377 So.2d 954 (Ala. 1979)), and the same rule produced a judgment for the owner in Cove Creek Development Corp. v. APAC-Alabama, Inc., 588 So.2d 458 (Ala. 1991), where the Court said Alabama has consistently enforced a per-diem liquidated-damages clause in a building contract, the sole caveat being that the clause must not be a penalty, and REVERSED a trial court that had found a 285-day delay totally excused by another contractor's interference, owner-initiated changes and unanticipated weather, rendering judgment for the owner because the contract itself addressed each of those delays and the contractor had sought only one extension under it. Equity recognises one exception, relieving a party of strict compliance with the time of performance, but it applies only where the contract does not expressly or implicitly, by its nature and purpose, make time an essential part of the agreement, and in Alpine Construction itself the exception was unavailable, because the contract expressly directed bidders' attention to the time required for completion and then specified liquidated damages for failure to complete on time (Alpine Construction, 377 So.2d 954).

    The trap

    The excuse is conditional, and the conditions are the ones parties forget: a seller who does not allocate fairly among customers, or does not give the buyer seasonable notice of the delay, nondelivery or quota, is outside § 7-2-615 whatever the event was. The buyer's side is conditional too: it must act "by written notification to the seller", and a buyer who neither terminates nor agrees to take its quota "within a reasonable time not exceeding 30 days" loses the affected deliveries by lapse. A force majeure clause can raise the seller's obligation above the statutory floor (the section opens "Except so far as a seller may have assumed a greater obligation"), and § 7-2-616(3) limits contracting out of the buyer's termination and substitution options to that same case. Outside Article 2 the clause is the whole defence, and an Alabama court reads it by its own list: the extension clause in Alpine Construction named changes ordered in writing, "fire, lightning, earthquake, tornado, cyclone, riot, insurrection or war", abandonment or discharge of workmen and default of another contractor, and allowed extra time only on written notice within five days "and thereupon, and not otherwise", so a delay in obtaining a specified material "does not fall within any of the categories of excused delay enumerated by the contract". An event the clause does not name, or a notice condition missed, leaves the promise absolute.

    as of 2026-09-17

    13 authorities

    • statuteAla. Code § 7-2-615enactment date not established
      Show the words that state the rule
      Except so far as a seller may have assumed a greater obligation and subject to Section 7-2-614 on substituted performance: (a) Delay in delivery or nondelivery in whole or in part by a seller who complies with paragraphs (b) and (c) is not a breach of his duty under a contract for sale if performance as agreed has been made impracticable by the occurrence of a contingency the nonoccurrence of which was a basic assumption on which the contract was made or by compliance in good faith with any applicable foreign or domestic governmental regulation or order whether or not it later proves to be invalid.
    • statuteAla. Code § 7-2-614enactment date not established
      Show the words that state the rule
      (1) Where without fault of either party the agreed berthing, loading, or unloading facilities fail or an agreed type of carrier becomes unavailable or the agreed manner of delivery otherwise becomes commercially impracticable but a commercially reasonable substitute is available, such substitute performance must be tendered and accepted.
    • statuteAla. Code § 7-2-616enactment date not established
      Show the words that state the rule
      (1) Where the buyer receives notification of a material or indefinite delay or an allocation justified under Section 7-2-615, he may by written notification to the seller as to any delivery concerned, and where the prospective deficiency substantially impairs the value of the whole contract under the provisions of this article relating to breach of installment contracts (Section 7-2-612), then also as to the whole: (a) Terminate and thereby discharge any unexecuted portion of the contract; or (b) Modify the contract by agreeing to take his available quota in substitution. (2) If after receipt of such notification from the seller the buyer fails so to modify the contract within a reasonable time not exceeding 30 days the contract lapses with respect to any deliveries affected. (3) The provisions of this section may not be negated by agreement except insofar as the seller has assumed a greater obligation under Section 7-2-615.
    • statuteAla. Code § 7-2-615enactment date not established
      Show the words that state the rule
      (b) Where the causes mentioned in paragraph (a) affect only a part of the seller’s capacity to perform, he must allocate production and deliveries among his customers but may at his option include regular customers not then under contract as well as his own requirements for further manufacture. He may so allocate in any manner which is fair and reasonable. (c) The seller must notify the buyer seasonably that there will be delay or nondelivery and, when allocation is required under paragraph (b), of the estimated quota thus made available for the buyer.
    • case377 So.2d 954Alpine Construction Co. v. Water Works Board of the City of BirminghamAla.decided 1979read it at the source ↗
      Show the words that state the rule
      Where one by his contract undertakes an obligation which is absolute, he is bound to perform within the terms of the contract or answer in damages, despite an act of God, unexpected difficulty, or hardship, because these contingencies could have been provided against by his contract.
    • case377 So.2d 954Alpine Construction Co. v. Water Works Board of the City of BirminghamAla.decided 1979read it at the source ↗
      Show the words that state the rule
      Alpine contends that its late performance is entitled to be excused under the doctrine of impossibility of performance, but fails to cite any Alabama cases in support of its position. Under Alabama law, a promisor is held strictly to the literal terms of his promise.
    • case377 So.2d 954Alpine Construction Co. v. Water Works Board of the City of BirminghamAla.decided 1979read it at the source ↗
      Show the words that state the rule
      It is true that equity recognizes an exception which generally will relieve a party of strict compliance with the time of performance in a contract; but this applies only where the contract does not expressly or implicitly, by its nature and purpose, make time an essential part of the agreement. Hunter-Benn & Co. Company v. Bassett Lumber Co., 224 Ala. 215, 139 So. 348 (1932). The contract before us expressly states that "[t]he attention of Bidders is especially directed to the time required for completion of the work required under this contract" and then goes on to specify liquidated damages for "failure to complete on time."
    • case377 So.2d 954Alpine Construction Co. v. Water Works Board of the City of BirminghamAla.decided 1979read it at the source ↗
      Show the words that state the rule
      Here, the trial Court held the contract to be clear and unambiguous and, as such, its interpretation was for the court and not for the jury. The contract provides for extensions of time, within the discretion of the contractee's engineer, for delays caused by construction changes ordered by the engineer, or by fire, lightning, earthquake, tornado, cyclone, riot, insurrection or war, and for on-site personnel or labor problems: "SEC. 20—EXTENSION OF TIME "The Contractor expressly covenants and agrees that in undertaking to complete the entire work within the time stated in the contract, he has taken into consideration and made allowance for all of the ordinary delays and hindrances incident to such work, whether growing out of delays in securing materials or workmen, or otherwise. Should the contractor, however, be substantially delayed in the prosecution and completion of the work by any changes, additions, or omissions therein ordered in writing by the Engineer, or by fire, lightning, earthquake, tornado, cyclone, riot, insurrection or war, or by the abandonment of the work by the workmen engaged therein through no fault of the Contractor, or by the discharge of all or any material number of workmen engaged therein through no fault of the Contractor, or by the discharge of all or any material number of workmen in consequence of difficulties arising between the Contractor and such workmen, or by the neglect, delay or default of any other Contractor of the Owner, the Contractor may, within five (5) days after the occurrence of the delay for which he claims allowance, notify the Engineer thereof in writing, and thereupon, and not otherwise, the Contractor shall be allowed such additional time for the completion of the work as the Engineer in his discretion shall award in writing."
    • case377 So.2d 954Alpine Construction Co. v. Water Works Board of the City of BirminghamAla.decided 1979read it at the source ↗
      Show the words that state the rule
      Thus, Alpine's reason for delay does not fall within any of the categories of excused delay enumerated by the contract, and the trial Court properly directed verdict for the Defendant on this issue. Moreover the record in this case discloses that Alpine was 401 days late in completing its contract which, at the rate of $100 per day would have amounted to $40,100 in liquidated damages instead of the $30,000 actually assessed. Alpine, in fact, received an extension of 101 days. AFFIRMED.
    • case588 So.2d 458Cove Creek Development Corp. v. APAC-Alabama, Inc.Ala.decided 1991read it at the source ↗
      Show the words that state the rule
      We hold that APAC's delays were not excusable and that it is bound by the contract and subject to the liquidated damages provision. Therefore, we hold that Cove Creek was within its rights under the liquidated damages provision to withhold $81,509.12 for the 285-day delay. Accordingly, the judgment of the trial court is reversed and a judgment is rendered in favor of Cove Creek. REVERSED AND JUDGMENT RENDERED.
    • case588 So.2d 458Cove Creek Development Corp. v. APAC-Alabama, Inc.Ala.decided 1991read it at the source ↗
      Show the words that state the rule
      Alabama has consistently enforced building contracts that contain liquidated damages provisions that specify that for each day's delay in completion beyond a fixed date the contractor will be liable for a fixed sum. The sole caveat in this enforcement is that the liquidated damages provision must not be a penalty.
    • case588 So.2d 458Cove Creek Development Corp. v. APAC-Alabama, Inc.Ala.decided 1991read it at the source ↗
      Show the words that state the rule
      The contract also provided for adjustments to the completion date made necessary by unavoidable delays, overruns, or additions to the contract: "In arriving at any credit due the contractor [APAC] for an extension of time on the contract, the owner [Cove Creek], upon the recommendation of the engineer, *Page 461 may allow such credit as in his judgment is deemed equitable and just for all delays occasioned by any act, or failure to act, on the part of the contractor or caused by forces beyond the contractor's control. Additional time will also be allowed the contractor to cover approved overruns or additions to the contract in the same proportion that the said over-runs or additions in monetary value bears to the original contract amount. ". . . . "Time extensions may be granted upon proper justification by the contractor. Any claim for time extensions under these provisions shall be submitted in writing to the engineer not more than twenty (20) days following commencement of the delay; otherwise the claim will be waived." The above provisions were the sole remedy provided in the contract for any delay in the construction.
    • case588 So.2d 458Cove Creek Development Corp. v. APAC-Alabama, Inc.Ala.decided 1991read it at the source ↗
      Show the words that state the rule
      As the above-quoted portion of the contract shows, all of the allegedly unavoidable delays were covered by the contract. APAC was apparently aware of these provisions regarding completion date extensions, because it took advantage of those provisions in obtaining a 45-day extension on the grounds that R M's utility work had caused it to abandon the construction site. Even with this extension, however, APAC completed its work under the contract 285 days late. Further, in spite of the fact that APAC was aware of the lengthening delay, APAC never sought any other extension under the contract.
  2. read at the 2026-10-03 bar

    Will this force-majeure / impossibility clause excuse late or non-performance under Alaska law?

    Yes, on two separate legal tracks that both land on the same substantive test. For a sale of goods, Alaska's UCC codifies the excuse directly: a seller's delay or nondelivery "is not a breach of the seller's duty under a contract for sale if performance as agreed has been made impracticable by the occurrence of a contingency, the nonoccurrence of which was a basic assumption on which the contract was made" or by good-faith compliance with a governmental regulation or order (AS 45.02.615(1)). For contracts generally, not limited to goods, Alaska's common law recognizes the same substantive idea under the banner of "commercial impracticability": Northern Corporation v. Chugach Electric Ass'n holds that "Alaska has adopted the Restatement doctrine whereby commercial impracticability may under certain circumstances justify regarding a contract as impossible to perform," discharging a party from its contract obligations, even where performance is technically possible, "if the costs of performance would be so disproportionate to that reasonably contemplated by the parties as to make the contract totally impractical in a commercial sense."

    The trap

    AS 45.02.615's excuse is qualified twice before it begins. It applies "[e]xcept so far as a seller may have assumed a greater obligation": a seller who contractually took on the risk of the very contingency that occurred gets no statutory excuse. It is also "subject to the preceding section on substituted performance," AS 45.02.614, and that section is mandatory the other way: where the agreed berthing, loading or carriage fails or the agreed manner of delivery "otherwise becomes commercially impracticable but a commercially reasonable substitute is available, the substitute performance must be tendered and accepted." A clause that recites impracticability does not excuse a seller who could have substituted. The statutory excuse also comes with affirmative duties the clause does not waive on its own: if the contingency affects only part of the seller's capacity, the seller must allocate production fairly and reasonably among customers (AS 45.02.615(2)), and must seasonably notify the buyer of the delay or nondelivery and, where allocation applies, of the buyer's estimated quota (AS 45.02.615(3)): silence can forfeit the excuse even where impracticability genuinely exists. On the common-law side, Northern Corp.'s test requires costs "so disproportionate" to what was contemplated as to be "totally impractical in a commercial sense": nothing read here quantifies that threshold, and ordinary cost increases or unprofitability, without more, are not shown by this authority to qualify. Note also what discharge bought the excused party in Northern Corp.: the owner that kept insisting on the impossible performance was "held liable for Northern's increased costs incurred after such time as Chugach was reasonably placed on notice" that the agreed method was not feasible, so an excuse clause can shift cost onto the party demanding performance rather than merely ending the deal.

    as of 2026-09-21

    7 authorities

    • statuteAS 45.02.615enactment date not established
      Show the words that state the rule
      Except so far as a seller may have assumed a greater obligation and subject to the preceding section on substituted performance, (1) delay in delivery or nondelivery in whole or in part by a seller who complies with (2) and (3) of this section is not a breach of the seller's duty under a contract for sale if performance as agreed has been made impracticable by the occurrence of a contingency, the nonoccurrence of which was a basic assumption on which the contract was made or by compliance in good faith with an applicable foreign or domestic governmental regulation or order whether or not it later proves to be invalid;
    • statuteAS 45.02.615enactment date not established
      Show the words that state the rule
      if the causes mentioned in (1) of this section affect only a part of the seller's capacity to perform, the seller must allocate production and deliveries among the seller's customers, but may at the seller's option include regular customers not then under contract as well as the seller's own requirements for further manufacture; the seller may so allocate in a manner that is fair and reasonable;
    • statuteAS 45.02.615enactment date not established
      Show the words that state the rule
      the seller must notify the buyer seasonably that there will be delay or nondelivery and, when allocation is required under (2) of this section, of the estimated quota thus made available for the buyer.
    • statuteAS 45.02.614enactment date not established
      Show the words that state the rule
      If without fault of either party the agreed berthing, loading, or unloading facilities fail or an agreed type of carrier becomes unavailable or the agreed manner of delivery otherwise becomes commercially impracticable but a commercially reasonable substitute is available, the substitute performance must be tendered and accepted.
    • case518 P.2d 76Northern Corporation v. Chugach Electric Ass'nAlaskadecided 1974read it at the source ↗
      Show the words that state the rule
      Alaska has adopted the Restatement doctrine whereby commercial impracticability may under certain circumstances justify regarding a contract as impossible to perform.
    • case518 P.2d 76Northern Corporation v. Chugach Electric Ass'nAlaskadecided 1974read it at the source ↗
      Show the words that state the rule
      a party is discharged from his contract obligations, even if it is technically possible to perform them, if the costs of performance would be so disproportionate to that reasonably contemplated by the parties as to make the contract totally impractical in a commercial sense.
    • case518 P.2d 76Northern Corporation v. Chugach Electric Ass'nAlaskadecided 1974read it at the source ↗
      Show the words that state the rule
      Despite the fact that no change order was actually issued by Chugach, we hold that it should be held liable for Northern’s increased costs incurred after such time as Chugach was reasonably placed on notice that it was not feasible to perform the contract by means of the ice haul method.
  3. read at the 2026-10-03 bar

    Does this force-majeure clause help or hurt, given California's statutory excuse?

    California supplies an excuse by statute whether or not the contract has a clause: performance is excused "to the extent to which they operate" when it is prevented or delayed by the act of the creditor or by the OPERATION OF LAW (even though there may have been a stipulation that this shall not be an excuse), and when it is prevented or delayed by an irresistible, superhuman cause or by the act of public enemies, UNLESS THE PARTIES HAVE EXPRESSLY AGREED TO THE CONTRARY, and when the debtor is induced not to perform by any act of the creditor intended or naturally tending to have that effect, done at or before the time performance may be made and not rescinded before that time (Civ. Code § 1511(1)-(3)). The same section permits a contract to require the party relying on the creditor-act/operation-of-law excuse to give written notice of its intention to claim an extension within a reasonable time, provided the notice requirement is reasonable and just.

    The trap

    The clause can subtract. Section 1511(2)'s excuse for an irresistible, superhuman cause is a default the parties may contract out of; whether an exhaustive 'force majeure means only the following events' list is that express contrary agreement is not answered by the statute or by any authority in this rule. The mirror-image trap is subdivision (1): a stipulation that prevention by operation of law is NOT an excuse is ineffective, but a reasonable written-notice condition IS effective, so the excuse can be lost for want of the notice the clause required. That is not merely the proviso's own words. Peter Kiewit Sons' Co. v. Pasadena City Junior College Dist. (1963) held that a provision requiring the contractor to apply for an extension of time before being excused for an owner-caused delay would constitute "a substantial limitation on the policy declared by section 1511"; Greg Opinski Construction, Inc. v. City of Oakdale (Cal. Ct. App. 2011) holds that this aspect of Peter Kiewit was superseded by a 1965 amendment to § 1511, that contractual procedures for requesting an extension of time can be the specification the amendment contemplates, and that a contractor who does not follow them cannot rely on Peter Kiewit at all. So the notice proviso is not a formality: it is the route by which a drafted clause takes back the subdivision (1) excuse the same subdivision says cannot be stipulated away.

    as of 2026-09-17

    3 authorities

    • statuteCal. Civ. Code § 1511enactment date not established
      Show the words that state the rule
      The want of performance of an obligation, or of an offer of performance, in whole or in part, or any delay therein, is excused by the following causes, to the extent to which they operate: 1. When such performance or offer is prevented or delayed by the act of the creditor, or by the operation of law, even though there may have been a stipulation that this shall not be an excuse; however, the parties may expressly require in a contract that the party relying on the provisions of this paragraph give written notice to the other party or parties, within a reasonable time after the occurrence of the event excusing performance, of an intention to claim an extension of time or of an intention to bring suit or of any other similar or related intent, provided the requirement of such notice is reasonable and just; 2. When it is prevented or delayed by an irresistible, superhuman cause, or by the act of public enemies of this state or of the United States, unless the parties have expressly agreed to the contrary; or, 3. When the debtor is induced not to make it, by any act of the creditor intended or naturally tending to have that effect, done at or before the time at which such performance or offer may be made, and not rescinded before that time.
    • case59 Cal. 2d 241Peter Kiewit Sons' Co. v. Pasadena City Junior College DistrictCal.decided 1963read it at the source ↗
      Show the words that state the rule
      An owner who is a party to a construction contract is a creditor within the meaning of section 1511 (Semas v. Bergmann, 178 Cal.App.2d 758, 762 [ 3 Cal.Rptr. 277 ]), and, as the italicized portion of the section makes clear, a provision in an agreement that the contractor is not to be excused for late completion caused by the owner is rendered inoperative by the statute. A provision in a contract which would require the contractor to make an application for an extension of time before he may be excused for a delay caused by the owner's conduct would obviously constitute a substantial limitation on the policy declared by section 1511.
    • caseNo. F060219 (Cal. Ct. App. Oct. 6, 2011)Greg Opinski Construction, Inc. v. City of OakdaleCal. Ct. App.decided 2011
      Show the words that state the rule
      In the published part of our opinion, we hold that this aspect of Peter Kiewit was superseded by a 1965 amendment to Civil Code section 1511, which allows parties to specify in a contract that a party intending to avoid the effect of its failure to perform by asserting that the other party’s act caused the failure must give written notice of this intention within a reasonable time. In this case, the contractual provisions requiring certain procedures to be followed by a party requesting an extension of time *1110 amounted to the type of specification contemplated by the amendment to Civil Code section 1511. Since Opinski did not follow those procedures to claim an extension of time, it cannot rely on Peter Kiewit, and the trial court was correct to enforce the procedural requirements of the contract.
  4. read at the 2026-10-03 bar

    Without a force majeure clause, will Connecticut excuse performance because of a government shutdown or pandemic?

    In AGW Sono Partners v. Downtown Soho (2022) the Connecticut Supreme Court held that the COVID-19 executive orders did not relieve a restaurant tenant of its lease obligations: the doctrine of impossibility or impracticability did not excuse performance (use of the premises was not rendered factually impossible where curbside or takeout service remained permitted and the lease did not prohibit it), and, given the narrowness of the frustration of purpose doctrine, the purpose of the lease was not frustrated even by orders that barred indoor dining entirely. The court noted the lease lacked a force majeure clause that would govern the parties' obligations in a crisis beyond their control.

    The trap

    AGW is a decision on one lease, not a rule that a government order can never excuse performance. The court said the restrictions 'simply raised the cost of performance for the defendants in a manner that rendered it perhaps highly burdensome, but not factually impossible', and it rested that on a lease that did not limit the tenant to a particular kind of dining and did not prohibit the takeout and outdoor service the orders still allowed. In its impossibility analysis the court also read the lease itself as suggesting that events of the magnitude of the pandemic were not entirely unforeseeable: the lease had no force majeure clause, and its only crisis clause (an 'unavoidable delay' provision) excused only the landlord's obligations. A tenant whose lease restricts use more tightly is not addressed by the holding.

    as of 2026-09-16

    8 authorities

    • case343 Conn. 309AGW Sono Partners, LLC v. Downtown Soho, LLCConn.decided 2022read it at the source ↗
      Show the words that state the rule
      Applying these principles, we conclude that the doc- trine of impossibility or impracticability did not excuse the defendants from their obligations to the plaintiff under the lease agreement.
    • case343 Conn. 309AGW Sono Partners, LLC v. Downtown Soho, LLCConn.decided 2022read it at the source ↗
      Show the words that state the rule
      Given the narrowness of the frustration of purpose doctrine, we conclude that the purpose of the lease agreement was not frustrated by the pandemic restric- tions imposed by the executive orders, even those that barred indoor dining entirely. The language of the lease agreement was not limited to a certain type of dining and—in contrast to the more restrictive language con- tained in the sister state cases on which the defendants rely—did not preclude the takeout and subsequent out- door dining that the defendants sought to provide. Put differently, the lease terms did not by themselves render the lease agreement valueless in light of the executive orders.
    • case343 Conn. 309AGW Sono Partners, LLC v. Downtown Soho, LLCConn.decided 2022read it at the source ↗
      Show the words that state the rule
      Second, the language of the lease agreement suggests that events of the magnitude of the COVID-19 pandemic were not entirely unforeseeable.
    • case343 Conn. 309AGW Sono Partners, LLC v. Downtown Soho, LLCConn.decided 2022read it at the source ↗
      Show the words that state the rule
      Although the COVID-19 restrictions had undoubtedly serious economic consequences for the viability of the bistro—in particular, the initial closure for indoor dining, followed by the loss of bar business and a reopening for indoor dining only with a drastic reduction in capacity—they did not, by themselves, make performance under the lease agreement impossi- ble or commercially impracticable as a matter of law.20 Instead, they simply raised the cost of performance for the defendants in a manner that rendered it perhaps highly burdensome, but not factually impossible—akin to the outbreak of war, or the closure of the Suez Canal, which had been held not to discharge contractual duties under the doctrine of impossibility.
    • case343 Conn. 309AGW Sono Partners, LLC v. Downtown Soho, LLCConn.decided 2022read it at the source ↗
      Show the words that state the rule
      First, and most significant, as the trial court found, even under the most restrictive executive orders, use of the premises for restaurant purposes was not rendered factually impossible insofar as restaurants were permitted to provide curbside or takeout service, and the lease agreement did not pro- hibit curbside or takeout service.
    • case343 Conn. 309AGW Sono Partners, LLC v. Downtown Soho, LLCConn.decided 2022read it at the source ↗
      Show the words that state the rule
      The lease agreement lacks a force majeure clause that would govern the parties’ mutual obligations in the event of a crisis situa- tion beyond their control,21 and, to the extent that the lease agreement provides for any forgiveness of obliga- tion in a crisis situation (thus suggesting that they are foreseeable), it excuses only the plaintiff’s obliga- tions—under § 25 of the lease agreement governing ‘‘unavoidable delay’’ occasioned by a variety of circum- stances, including fire or ‘‘governmental [preemption] in connection with a national emergency . . . .’’
    • case343 Conn. 309AGW Sono Partners, LLC v. Downtown Soho, LLCConn.decided 2022read it at the source ↗
      Show the words that state the rule
      The judgment is reversed only with respect to the award of damages and the case is remanded for further proceedings as to damages; the judgment is affirmed in all other respects.
    • case343 Conn. 309AGW Sono Partners, LLC v. Downtown Soho, LLCConn.decided 2022read it at the source ↗
      Show the words that state the rule
      To the extent that our independent research has found authority that excused—at least in part—tenants from their rental obligations during COVID-19, that authority rests on distinguishable lease language, namely, force majeure clauses that governed this particular situation.
  5. read at the 2026-10-03 bar

    Will this force-majeure / impossibility / frustration-of-purpose clause excuse late or non-performance in Idaho?

    It depends on what the contract is for. For a SALE OF GOODS Idaho does codify an excuse, and it is a standard rather than a list of events: Idaho Code § 28-2-615, "[e]xcept so far as a seller may have assumed a greater obligation and subject to the preceding section on substituted performance," makes delay or nondelivery no breach of the seller's duty where "performance as agreed has been made impracticable by the occurrence of a contingency the nonoccurrence of which was a basic assumption on which the contract was made or by compliance in good faith with any applicable foreign or domestic governmental regulation or order whether or not it later proves to be invalid." The section that precedes it goes first in order: under § 28-2-614(1), where the agreed manner of delivery "otherwise becomes commercially impracticable but a commercially reasonable substitute is available, such substitute performance must be tendered and accepted." Outside the sales article there is no general excuse-of-performance statute: Idaho's contracts chapter runs §§ 29-101 to 29-116 and carries none, so for a services, construction or real-property contract the doctrine rests on Idaho common law. Rasmussen v. Martin states the controlling common-law standard: "As a general rule, relief from a provision of a contract, in order to avoid frustration of the contract's underlying purpose, will not be granted where the claimed grounds of frustration are merely personal to one of the parties. The frustration must be objective, rather than subjective, in nature."

    The trap

    The objective/subjective line is the whole doctrine and is easy to blur in practice (Rasmussen itself denied the defense where the claimed frustration was that the parties' relationship "has so deteriorated that they 'are unable to trust each other'"), personal to the parties, not an objective impediment to performance: "the record does not contain a showing of objective frustration," and "[t]he district court did not find that Rasmussen was untrustworthy." A party whose own circumstances, or feelings about the counterparty, make performance unwelcome does not get the defense merely by invoking "frustration." Outside a goods contract there is no Idaho statute on point, so a drafter cannot point to a fixed statutory list of qualifying events, and the doctrine's content is defined by case-by-case application of the objective/subjective distinction, which makes a well-drafted contractual force-majeure clause listing specific qualifying events comparatively more important in Idaho than in a state with a statutory backstop, precisely because there is no statutory default to fall back on. Inside a goods contract the opposite trap applies. § 28-2-615 is a default the contract can displace, since it yields "so far as a seller may have assumed a greater obligation", and the protection is conditional on the seller's own conduct: it must "allocate production and deliveries among his customers" where only part of its capacity is affected, and must "notify the buyer seasonably that there will be delay or nondelivery", so a seller that simply stops shipping and tells nobody loses the excuse. The common-law half of this rule rests on a single 1983 Court of Appeals decision, which sustained the district court and affirmed. Across every published Idaho opinion the phrase "objective frustration" appears in that decision and nowhere else, and of the six opinions that mention frustration of purpose none is a later Idaho Supreme Court decision applying the objective/subjective test to a commercial contract: one barred the defence by collateral estoppel from a federal bankruptcy ruling, one excluded it as raised too late, and the only later citation of the test is a Court of Appeals parenthetical in a bail-bond case.

    as of 2026-09-21

    7 authorities

    • statuteIdaho Code § 28-2-615enactment date not established
      Show the words that state the rule
      Except so far as a seller may have assumed a greater obligation and subject to the preceding section on substituted performance: (a) Delay in delivery or nondelivery in whole or in part by a seller who complies with paragraphs (b) and (c) is not a breach of his duty under a contract for sale if performance as agreed has been made impracticable by the occurrence of a contingency the nonoccurrence of which was a basic assumption on which the contract was made or by compliance in good faith with any applicable foreign or domestic governmental regulation or order whether or not it later proves to be invalid.
    • statuteIdaho Code § 28-2-615enactment date not established
      Show the words that state the rule
      (b) Where the causes mentioned in paragraph (a) affect only a part of the seller’s capacity to perform, he must allocate production and deliveries among his customers but may at his option include regular customers not then under contract as well as his own requirements for further manufacture. He may so allocate in any manner which is fair and reasonable. (c) The seller must notify the buyer seasonably that there will be delay or nondelivery and, when allocation is required under paragraph (b), of the estimated quota thus made available for the buyer.
    • statuteIdaho Code § 28-2-614enactment date not established
      Show the words that state the rule
      Where without fault of either party the agreed berthing, loading, or unloading facilities fail or an agreed type of carrier becomes unavailable or the agreed manner of delivery otherwise becomes commercially impracticable but a commercially reasonable substitute is available, such substitute performance must be tendered and accepted.
    • case659 P.2d 155Rasmussen v. MartinIdaho Ct. App.decided 1983read it at the source ↗
      Show the words that state the rule
      As a general rule, relief from a provision of a contract, in order to avoid frustration of the contract’s underlying purpose, will not be granted where the claimed grounds of frustration are merely personal to one of the parties. The frustration must be objective, rather than subjective, in nature.
    • case659 P.2d 155Rasmussen v. MartinIdaho Ct. App.decided 1983read it at the source ↗
      Show the words that state the rule
      In his brief on appeal, Martin’s counsel argues that the relationship between the parties has so deteriorated that they “are unable to trust each other.”
    • case659 P.2d 155Rasmussen v. MartinIdaho Ct. App.decided 1983read it at the source ↗
      Show the words that state the rule
      In this case, the record does not contain a showing of objective frustration. The district court did not find that Rasmussen was untrustworthy.
    • case659 P.2d 155Rasmussen v. MartinIdaho Ct. App.decided 1983read it at the source ↗
      Show the words that state the rule
      Upon this record, we sustain the district court’s ruling that Rasmussen’s obligation to provide future services should not be treated as a present debt. The judgment of the district court is affirmed. Costs, but no attorney fees, to respondents Rasmussen.
  6. read at the 2026-10-03 bar

    Will this force majeure clause excuse performance in Illinois?

    For a seller of goods, Illinois has the uniform statutory excuse, which by its opening line applies 'Except so far as a seller may have assumed a greater obligation and subject to the preceding section on substituted performance': delay or non-delivery is not a breach if performance as agreed has been made impracticable by the occurrence of a contingency the non-occurrence of which was a basic assumption on which the contract was made, or by compliance in good faith with any applicable foreign or domestic governmental regulation or order 'whether or not it later proves to be invalid', provided the seller allocates production fairly among customers and seasonably notifies the buyer (810 ILCS 5/2-615). No Illinois decision construing a force majeure CLAUSE is quoted here. The "preceding section" it yields to requires a commercially reasonable substitute to be tendered and accepted where agreed facilities, carriers or the manner of delivery fail (810 ILCS 5/2-614(1)); its second subsection is a payment rule a force majeure clause rarely reaches, for if the agreed means or manner of payment fails because of domestic or foreign governmental regulation the seller may withhold or stop delivery unless the buyer provides a commercially substantially equivalent substitute, and once delivery has been taken payment in the manner the regulation provides discharges the buyer "unless the regulation is discriminatory, oppressive or predatory" (§ 2-614(2)); and the section after it gives the buyer the election, by written notification to the seller as to any delivery concerned, and, where the prospective deficiency substantially impairs the value of the whole contract under the installment-contract provisions (§ 2-612), as to the whole: on notice of a material or indefinite delay or an allocation, to terminate the unexecuted portion or take the quota in substitution; silence for a reasonable time not exceeding 30 days lapses the affected deliveries; and that section "may not be negated by agreement" except where the seller has assumed a greater obligation (810 ILCS 5/2-616).

    The trap

    Section 2-615 is a default for sellers, not a reading of the parties' clause (its own text yields where the seller 'may have assumed a greater obligation'), and it comes with duties the clause usually omits: fair and reasonable allocation among customers, and seasonable notice of the delay and of the buyer's estimated quota. Outside Article 2 the Illinois rule is unread rather than absent, and the honest statement is a measured one: across Illinois case law 17 opinions contain the phrase force majeure in lower case and 3 more contain it capitalised (the capitalised-first-word spelling returns none), and every one of the nine the scan listed by name is an Appellate Court decision, among them 55 Jackson Acquisition v. Roti Restaurants (2022), Wermers Floorcovering v. Santanna Natural Gas (2003) and Schawk v. Donruss Trading Cards (2001). Not one of the twenty has been read, so how an Illinois court construes a force majeure list, a catch-all naming causes and then adding others of the same kind, or an epidemic or government-order clause is not stated here; what cannot be said is that there is nothing to find.

    as of 2026-09-17

    5 authorities

    • statute810 ILCS 5/2-615enactment date not established
      Show the words that state the rule
      Except so far as a seller may have assumed a greater obligation and subject to the preceding section on substituted performance: (a) Delay in delivery or non-delivery in whole or in part by a seller who complies with paragraphs (b) and (c) is not a breach of his duty under a contract for sale if performance as agreed has been made impracticable by the occurrence of a contingency the non-occurrence of which was a basic assumption on which the contract was made or by compliance in good faith with any applicable foreign or domestic governmental regulation or order whether or not it later proves to be invalid.
    • statute810 ILCS 5/2-615enactment date not established
      Show the words that state the rule
      (b) Where the causes mentioned in paragraph (a) affect only a part of the seller's capacity to perform, he must allocate production and deliveries among his customers but may at his option include regular customers not then under contract as well as his own requirements for further manufacture. He may so allocate in any manner which is fair and reasonable. (c) The seller must notify the buyer seasonably that there will be delay or non-delivery and, when allocation is required under paragraph (b), of the estimated quota thus made available for the buyer.
    • statute810 ILCS 5/2-614enactment date not established
      Show the words that state the rule
      (1) Where without fault of either party the agreed berthing, loading, or unloading facilities fail or an agreed type of carrier becomes unavailable or the agreed manner of delivery otherwise becomes commercially impracticable but a commercially reasonable substitute is available, such substitute performance must be tendered and accepted.
    • statute810 ILCS 5/2-616enactment date not established
      Show the words that state the rule
      (1) Where the buyer receives notification of a material or indefinite delay or an allocation justified under the preceding section he may by written notification to the seller as to any delivery concerned, and where the prospective deficiency substantially impairs the value of the whole contract under the provisions of this Article relating to breach of installment contracts (Section 2-612), then also as to the whole, (a) terminate and thereby discharge any unexecuted portion of the contract; or (b) modify the contract by agreeing to take his available quota in substitution. (2) If after receipt of such notification from the seller the buyer fails so to modify the contract within a reasonable time not exceeding 30 days the contract lapses with respect to any deliveries affected. (3) The provisions of this Section may not be negated by agreement except in so far as the seller has assumed a greater obligation under the preceding section.
    • statute810 ILCS 5/2-614enactment date not established
      Show the words that state the rule
      (2) If the agreed means or manner of payment fails because of domestic or foreign governmental regulation, the seller may withhold or stop delivery unless the buyer provides a means or manner of payment which is commercially a substantial equivalent. If delivery has already been taken, payment by the means or in the manner provided by the regulation discharges the buyer's obligation unless the regulation is discriminatory, oppressive or predatory.
  7. read at the 2026-10-03 bar

    Does our force majeure clause excuse performance under Iowa law?

    For a sale of goods, Iowa Code § 554.2615 supplies a seller's excuse the clause does not have to create, and it opens with its own limits: "Except so far as a seller may have assumed a greater obligation and subject to section 554.2614 on substituted performance", delay in delivery or nondelivery in whole or in part by a seller who complies with subsections 2 and 3 is not a breach of the seller's duty if performance as agreed has been made impracticable by the occurrence of a contingency the nonoccurrence of which was a basic assumption on which the contract was made, or by compliance in good faith with any applicable foreign or domestic governmental regulation or order whether or not it later proves to be invalid. Where the causes affect only part of the seller's capacity, the seller must allocate production and deliveries among its customers "but may at the seller's option include regular customers not then under contract as well as the seller's own requirements for further manufacture", and may so allocate in any manner which is fair and reasonable (§ 554.2615(2)), and it must notify the buyer seasonably of the delay or nondelivery and, where allocation is required, of the estimated quota made available to that buyer. Section 554.2614, which the excuse is expressly subject to, can take the case away before impracticability is reached: where the agreed berthing, loading or unloading facilities fail, or an agreed type of carrier becomes unavailable, or the agreed manner of delivery otherwise becomes commercially impracticable, "but a commercially reasonable substitute is available, such substitute performance must be tendered and accepted."

    The trap

    The statutory excuse is conditional and one-sided on the section's words. It runs to a SELLER, and only to a seller "who complies with subsections 2 and 3": fair and reasonable allocation and seasonable notice are conditions of the excuse, not courtesies. A clause by which the seller assumes a greater obligation takes the case outside the section by its opening words, so a drafter who promises delivery come what may has contracted out of it. The other half of that opening points at the seller: a commercially reasonable substitute "must be tendered and accepted" under § 554.2614(1), so an excuse argued without trying the substitute is argued too early. And nothing in § 554.2615 excuses a buyer, or a party to a contract that is not a sale of goods; no Iowa authority on common-law impossibility or frustration outside article 2 is cited in this rule.

    as of 2026-09-19

    4 authorities

    • statuteIowa Code § 554.2615enactment date not established
      Show the words that state the rule
      Except so far as a seller may have assumed a greater obligation and subject to section 554.2614 on substituted performance: 1. Delay in delivery or nondelivery in whole or in part by a seller who complies with subsections 2 and 3, is not a breach of the seller’s duty under a contract for sale if performance as agreed has been made impracticable by the occurrence of a contingency the nonoccurrence of which was a basic assumption on which the contract was made or by compliance in good faith with any applicable foreign or domestic governmental regulation or order whether or not it later proves to be invalid.
    • statuteIowa Code § 554.2615enactment date not established
      Show the words that state the rule
      Where the causes mentioned in subsection 1 affect only a part of the seller’s capacity to perform, the seller must allocate production and deliveries among the seller’s customers but may at the seller’s option include regular customers not then under contract as well as the seller’s own requirements for further manufacture. The seller may so allocate in any manner which is fair and reasonable.
    • statuteIowa Code § 554.2615enactment date not established
      Show the words that state the rule
      The seller must notify the buyer seasonably that there will be delay or nondelivery and, when allocation is required under subsection 2, of the estimated quota thus made available for the buyer.
    • statuteIowa Code § 554.2614enactment date not established
      Show the words that state the rule
      Where without fault of either party the agreed berthing, loading, or unloading facilities fail or an agreed type of carrier becomes unavailable or the agreed manner of delivery otherwise becomes commercially impracticable but a commercially reasonable substitute is available, such substitute performance must be tendered and accepted.
  8. read at the 2026-10-03 bar

    Does our force majeure clause excuse performance under Kansas law?

    For a sale of goods, K.S.A. 84-2-615 supplies a seller's excuse the clause does not have to create, and it opens with its own limits: "Except so far as a seller may have assumed a greater obligation and subject to the preceding section on substituted performance", delay in delivery or nondelivery in whole or in part by a seller who complies with paragraphs (b) and (c) is not a breach of the seller's duty if performance as agreed has been made impracticable by the occurrence of a contingency the nonoccurrence of which was a basic assumption on which the contract was made, or by compliance in good faith with any applicable foreign or domestic governmental regulation or order whether or not it later proves to be invalid. Where the causes affect only part of the seller's capacity, the seller must allocate production and deliveries among its customers in any manner which is fair and reasonable, and must notify the buyer seasonably of the delay or non-delivery and, where allocation is required, of the estimated quota made available to that buyer. The section the excuse is expressly subject to carries its own command: where without fault of either party the agreed berthing, loading or unloading facilities fail, an agreed type of carrier becomes unavailable, or the agreed manner of delivery otherwise becomes commercially impracticable, but a commercially reasonable substitute is available, "such substitute performance must be tendered and accepted" (K.S.A. 84-2-614(1)).

    The trap

    The statutory excuse is conditional and one-sided on the section's words. It runs to a SELLER, and only to a seller "who complies with paragraphs (b) and (c)": fair and reasonable allocation and seasonable notice are conditions of the excuse, not courtesies. A clause by which the seller assumes a greater obligation takes the case outside the section by its opening words, so a promise to deliver whatever happens is a contracting-out. And nothing in K.S.A. 84-2-615 excuses a buyer, or a party to a contract that is not a sale of goods. Outside article 2 the doctrine Kansas states is frustration of purpose, and it is the Restatement's: the decision that states it is a plea-agreement case, Kansas applying contract principles to plea agreements, and the party invoking the doctrine there LOST: in State v. Boley the Supreme Court set out Restatement (Second) of Contracts § 265, that where a party's principal purpose is substantially frustrated without its fault by the occurrence of an event the non-occurrence of which was a basic assumption on which the contract was made, "his remaining duties to render performance are discharged, unless the language or the circumstances indicate the contrary", and then applied three elements from comment a: that the frustrated purpose was "so completely the basis of the contract that . . . without it the transaction would make little sense", that "the frustration must be substantial" and "so severe that it is not fairly to be regarded as within the risks . . . assumed under the contract", and that the "nonoccurrence of the frustrating event must have been a basic assumption on which the contract was made." That second element is where the argument died in Boley itself: "It is not enough that the transaction has become less profitable for the affected parly or even that [it] will sustain a loss." The State "does not meet the second element of the frustration of purpose doctrine because the frustration was not “so severe”"; the risk it complained of "was foreseeable and, admittedly, foreseen"; and the Court concluded that "the elements of the frustration of purpose doctrine were not met under the facts of this case." The drafting lesson is in the same passage: the party who bore the risk "could have protected against this risk by including a provision" dealing with it, which is what a force-majeure clause is for.

    as of 2026-10-08

    11 authorities

    • statuteK.S.A. 84-2-615enactment date not established
      Show the words that state the rule
      Except so far as a seller may have assumed a greater obligation and subject to the preceding section on substituted performance: (a) Delay in delivery or nondelivery in whole or in part by a seller who complies with paragraphs (b) and (c) is not a breach of his duty under a contract for sale if performance as agreed has been made impracticable by the occurrence of a contingency the nonoccurrence of which was a basic assumption on which the contract was made or by compliance in good faith with any applicable foreign or domestic governmental regulation or order whether or not it later proves to be invalid.
    • statuteK.S.A. 84-2-615enactment date not established
      Show the words that state the rule
      Where the causes mentioned in paragraph (a) affect only a part of the seller's capacity to perform, he must allocate production and deliveries among his customers but may at his option include regular customers not then under contract as well as his own requirements for further manufacture. He may so allocate in any manner which is fair and reasonable.
    • statuteK.S.A. 84-2-615enactment date not established
      Show the words that state the rule
      The seller must notify the buyer seasonably that there will be delay or non-delivery and, when allocation is required under paragraph (b), of the estimated quota thus made available for the buyer.
    • case113 P.3d 248State v. BoleyKan.decided 2005read it at the source ↗
      Show the words that state the rule
      The frustration of purpose doctrine is stated in the Restatement (Second) of Contracts § 265 (1979): “Where, after a contract- is made, a party’s principal purpose is substantially frustrated without his fault by the occurrence of an event the non-occurrence of which was a basic assumption on which the contract was made, his remaining duties to render performance are discharged, unless the language or the circumstances indicate the contrary.”
    • case113 P.3d 248State v. BoleyKan.decided 2005read it at the source ↗
      Show the words that state the rule
      The first step in applying the doctrine is to determine whether the frustrated purpose was “so completely the basis of the contract that . . . without it the transaction would make little sense.” Restatement (Second) of Contracts § 265, comment a.
    • case113 P.3d 248State v. BoleyKan.decided 2005read it at the source ↗
      Show the words that state the rule
      The Restatement defines the second element of the doctrine by stating: “[T]he frustration must be substantial. It is not enough that the transaction has become less profitable for the affected parly or even that [it] will sustain a loss. The frustration must be so severe that it is not fairly to be regarded as within the risks . . . assumed under the contract.” Restatement (Second) of Contracts § 265, comment a.
    • case113 P.3d 248State v. BoleyKan.decided 2005read it at the source ↗
      Show the words that state the rule
      The third and final element of the doctrine is that the “nonoccurrence of the frustrating event must have been a basic assumption on which the contract was made.” Restatement (Second) of Contracts § 265, comment a.
    • case113 P.3d 248State v. BoleyKan.decided 2005read it at the source ↗
      Show the words that state the rule
      Thus, the State does not meet the second element of the frustration of purpose doctrine because the frustration was not “so severe” that it is fairly regarded as within the risks assumed under the contract. Restatement (Second) of Contracts § 265, comment a.
    • case113 P.3d 248State v. BoleyKan.decided 2005read it at the source ↗
      Show the words that state the rule
      The risk that Boley could only be sentenced to the lesser penalty was foreseeable and, admittedly, foreseen. Thus, contraiy to the Boley Court of Appeals’ holding, we conclude that the elements of the frustration of purpose doctrine were not met under the facts of this case.
    • case113 P.3d 248State v. BoleyKan.decided 2005read it at the source ↗
      Show the words that state the rule
      The prosecutor could have protected against this risk by including a provision in the plea agreement requiring the defendant to waive his right to appeal or indicating that if the defendant successfully challenged his sentence, such action would be considered a breach of the agreement.
    • statuteK.S.A. 84-2-614enactment date not established
      Show the words that state the rule
      (1) Where without fault of either party the agreed berthing, loading, or unloading facilities fail or an agreed type of carrier becomes unavailable or the agreed manner of delivery otherwise becomes commercially impracticable but a commercially reasonable substitute is available, such substitute performance must be tendered and accepted.
  9. read at the 2026-10-03 bar

    Will a Louisiana court excuse late or non-performance under this force-majeure clause, or under the Civil Code even with no clause at all?

    Louisiana’s doctrine for excused non-performance is not force majeure but "fortuitous event" (cas fortuit), and it excuses performance by operation of law even in a contract that says nothing about it. The Civil Code is not silent on the words force majeure, so do not treat their absence as the reason: arts. 577, 583 and 613 use them, art. 583 being headed "Ruin from accident, force majeure , or age" with the space before the comma exactly as published. Those are usufruct articles, and none of them governs performance of a conventional obligation, so a Louisiana force-majeure clause is measured against arts. 1873 to 1878 and not against any Code definition of its own name. Civil Code art. 1873: "An obligor is not liable for his failure to perform when it is caused by a fortuitous event that makes performance impossible." Article 1875 supplies the definition, and it is a FORESEEABILITY test measured at formation: "A fortuitous event is one that, at the time the contract was made, could not have been reasonably foreseen." If the event destroys the ENTIRE performance owed, art. 1876 dissolves the contract outright: "When the entire performance owed by one party has become impossible because of a fortuitous event, the contract is dissolved." The same article then orders restitution: "The other party may then recover any performance he has already rendered." The one Louisiana opinion cited here does NOT apply the doctrine, and should not be read as if it did: in Creole Gardens, L.L.C. v. Schreiber the Fourth Circuit quoted arts. 1994, 1873 and 1986 only as the appellant's argument for a French-style "obligation of result" ("Creole Gardens contends the obligation of result concept is supported by La. C.C. arts. 1994, 1873, and 1986, which, when read in paria materia, holds the obligor liable ... unless the failure to perform was caused by a fortuitous event") and rejected the argument ("notwithstanding that confluence and any theoretical support for the doctrine provided by La. C.C. articles 1994, 1873, and 1986, Creole Gardens' argument that the district court committed legal error in not applying the obligation of result doctrine is fundamentally flawed") deciding the case under the redhibition articles instead and affirming the judgment against Creole Gardens. This rule therefore rests on the Code's own text; no opinion excusing a commercial obligor under art. 1873 is cited, and that gap is stated rather than papered over.

    The trap

    The Code's own liability-preserving exceptions inside art. 1873 are easy to miss when a drafter assumes "impossible" always wins: an obligor who ASSUMED THE RISK of the fortuitous event is liable anyway; an obligor who was already IN DEFAULT when the event struck is liable; and an obligor whose own prior FAULT preceded and contributed to the failure is liable: the article states all three as exceptions in the same breath as the general excuse. Partial impossibility does not automatically dissolve the whole deal: art. 1877, "the court may reduce the other party's counterperformance proportionally, or, according to the circumstances, may declare the contract dissolved". Reduction, not automatic dissolution, is the Code's own first-listed option. And a fortuitous event that strikes AFTER partial performance does not erase what has already changed hands: art. 1878 binds the obligee "only to the extent that he was enriched by the obligor's partial performance," a restitution-style, not all-or-nothing, remedy. Finally, art. 1875's foreseeability test is fixed at CONTRACT FORMATION: an event that was foreseeable when the parties signed does not become a fortuitous event later just because it in fact was not anticipated by the party invoking it.

    as of 2026-09-21

    10 authorities

    • statuteLa. Civ. Code art. 1873enactment date not established
      Show the words that state the rule
      An obligor is not liable for his failure to perform when it is caused by a fortuitous event that makes performance impossible.
    • statuteLa. Civ. Code art. 1875enactment date not established
      Show the words that state the rule
      A fortuitous event is one that, at the time the contract was made, could not have been reasonably foreseen.
    • statuteLa. Civ. Code art. 1876enactment date not established
      Show the words that state the rule
      When the entire performance owed by one party has become impossible because of a fortuitous event, the contract is dissolved. The other party may then recover any performance he has already rendered.
    • statuteLa. Civ. Code art. 1877enactment date not established
      Show the words that state the rule
      When a fortuitous event has made a party's performance impossible in part, the court may reduce the other party's counterperformance proportionally, or, according to the circumstances, may declare the contract dissolved.
    • caseNo. 2019-CA-0105 (La. Ct. App. 4th Cir. Sept. 25, 2019)Creole Gardens, L.L.C. v. Klaus-Peter F. Schreiber and Sarah Leonard SchreiberLa. Ct. App.decided 2019
      Show the words that state the rule
      Creole Gardens contends the obligation of result concept is supported by La. C.C. arts. 1994, 1873, and 1986, which, when read in paria materia, holds the obligor liable to the obligee for damages arising out of the obligor’s failure to perform a conventional obligation, unless the failure to perform was caused by a fortuitous event.
    • caseNo. 2019-CA-0105 (La. Ct. App. 4th Cir. Sept. 25, 2019)Creole Gardens, L.L.C. v. Klaus-Peter F. Schreiber and Sarah Leonard SchreiberLa. Ct. App.decided 2019
      Show the words that state the rule
      notwithstanding that confluence and any theoretical support for the doctrine provided by La. C.C. articles 1994, 1873, and 1986, Creole Gardens’ argument that the district court committed legal error in not applying the obligation of result doctrine is fundamentally flawed.
    • caseNo. 2019-CA-0105 (La. Ct. App. 4th Cir. Sept. 25, 2019)Creole Gardens, L.L.C. v. Klaus-Peter F. Schreiber and Sarah Leonard SchreiberLa. Ct. App.decided 2019
      Show the words that state the rule
      We conclude that Creole Gardens’ Petition asserts redhibition claims, contractual in nature, arising from an alleged breach of warranty of the thing sold by the sellers, the Schreibers. La. C.C. art. 2548 clearly delineates Creole Gardens’ rights as the buyer to acquire property free of redhibitory defects known by the Schreibers in an “as is” sale. Consequently, we find no legal error in the district court’s reliance on our redhibition statutes, particularly, La. C.C. art. 2548, to determine the Schreibers’ breach of warranty against fire code violations and Creole Gardens’ burden of proof. Accordingly, this assignment of error lacks merit.
    • statuteLa. Civ. Code art. 1873enactment date not established
      Show the words that state the rule
      An obligor is, however, liable for his failure to perform when he has assumed the risk of such a fortuitous event. An obligor is liable also when the fortuitous event occurred after he has been put in default. An obligor is likewise liable when the fortuitous event that caused his failure to perform has been preceded by his fault, without which the failure would not have occurred.
    • statuteLa. Civ. Code art. 1878enactment date not established
      Show the words that state the rule
      If a contract is dissolved because of a fortuitous event that occurred after an obligor has performed in part, the obligee is bound but only to the extent that he was enriched by the obligor's partial performance.
    • statuteLa. Civ. Code art. 583enactment date not established
      Show the words that state the rule
      Art. 583. Ruin from accident, force majeure , or age Neither the usufructuary nor the naked owner is bound to restore property that has been totally destroyed through accident, force majeure , or age.
  10. read at the 2026-10-03 bar

    Will this force-majeure clause excuse our performance in Maine?

    Only to the extent the clause's own words say so, and the party invoking it carries the burden. In 55 Oak Street LLC v. RDR Enterprises, Inc. the Law Court held that "[a] force majeure clause is a provision in a contract providing that certain supervening events may excuse a party's performance obligations", that "[w]hether a force majeure clause applies to excuse a party's performance depends on the clause's language", and that "[u]nless otherwise indicated by the contract, the party seeking to have its nonperformance excused by the force majeure clause bears the burden of proof". The Court vacated a judgment for a tenant whose rent had been partly excused, because the District Court "read the lease's force majeure clause as partially excusing RDR Enterprises' obligation to pay rent and concluded that RDR Enterprises did not breach the terms of the lease. This conclusion, however, is contrary to the unambiguous terms of the lease", and remanded for entry of a writ of possession for the landlord. For a sale of goods the answer is different, and the statute requires proportional performance rather than forbidding it. 11 M.R.S. § 2-615(1) excuses "[d]elay in delivery or nondelivery in whole or in part by a seller who complies with subsections (2) and (3)" where performance "has been made impracticable by the occurrence of a contingency the nonoccurrence of which was a basic assumption on which the contract was made" or by good-faith compliance with a governmental regulation or order, and subsection (2) then says that where the cause "affect[s] only a part of the seller's capacity to perform, he must allocate production and deliveries among his customers", while subsection (3) requires seasonable notice of the delay and of the buyer's estimated quota.

    The trap

    The Maine trap is proportional relief, and it runs in opposite directions for a lease and for goods. For a lease: a clause drafted in the usual all-or-nothing form ("[n]either party hereto will be liable for any failure to comply or delay in complying with its obligations hereunder") does not authorise a court to discount the rent to the fraction of capacity the event left. That is what 55 Oak Street reversed. Read that holding narrowly, though: the tenant there "did not pay any of the rent owed", and the Court's own footnote says that "even if the concept of a partial excuse for nonperformance were applicable, nothing in the lease's force majeure clause—or any other part of the lease—indicates that the obligation to pay the amount due under the lease would be completely discharged when part of the tenant's duty to pay rent is excused". So Maine has not held that partial excuse is unavailable; it has held that this lease did not provide for it and that paying nothing was a default. If partial or pro-rata relief is what the parties want, the clause has to say so. For goods the Code goes the other way: a seller who wants § 2-615's excuse MUST allocate among customers when only part of its capacity is hit and MUST give seasonable notice, so refusing to supply anyone is not a safe course; and on receiving notice of a material delay or an allocation the buyer may "[t]erminate and thereby discharge any unexecuted portion of the contract" or take its quota in substitution, with the contract lapsing as to affected deliveries if the buyer does not modify "within a reasonable time not exceeding 30 days", and § 2-616(3) says those provisions "may not be negated by agreement" except where the seller assumed a greater obligation. Note also that 55 Oak Street decided the case on the clause's language and expressly did NOT reach whether the force-majeure event proximately caused the failure to pay, so Maine's causation requirement is not settled by the decisions read; and § 2-615 runs to a seller of goods, not to a buyer's payment obligation.

    as of 2026-09-20

    14 authorities

    • case2022 ME 2855 Oak Street LLC v. RDR Enterprises, Inc.Me.decided 2022read it at the source ↗
      Show the words that state the rule
      A force majeure clause is a provision in a contract providing that certain supervening events may excuse a party’s performance obligations.
    • case2022 ME 2855 Oak Street LLC v. RDR Enterprises, Inc.Me.decided 2022read it at the source ↗
      Show the words that state the rule
      Whether a force majeure clause applies to excuse a party’s performance depends on the clause’s language.
    • case2022 ME 2855 Oak Street LLC v. RDR Enterprises, Inc.Me.decided 2022read it at the source ↗
      Show the words that state the rule
      Unless otherwise indicated by the contract, the party seeking to have its nonperformance excused by the force majeure clause bears the burden of proof.
    • case2022 ME 2855 Oak Street LLC v. RDR Enterprises, Inc.Me.decided 2022read it at the source ↗
      Show the words that state the rule
      The District Court denied Oak Street’s complaint because it read the lease’s force majeure clause as partially excusing RDR Enterprises’ obligation to pay rent and concluded that RDR Enterprises did not breach the terms of the lease. This conclusion, however, is contrary to the unambiguous terms of the lease.
    • case2022 ME 2855 Oak Street LLC v. RDR Enterprises, Inc.me-medecided 2022read it at the source ↗
      Show the words that state the rule
      Our conclusion that Oak Street is entitled to possession of the property is further supported by 10 the fact that RDR Enterprises did not pay any of the rent owed. The language of the lease unambiguously provides that a failure to pay rent constitutes grounds for default of the lease. This means all the rent due. Hence, even if the concept of a partial excuse for nonperformance were applicable, nothing in the lease’s force majeure clause—or any other part of the lease—indicates that the obligation to pay the amount due under the lease would be completely discharged when part of the tenant’s duty to pay rent is excused by a force majeure event.
    • case2022 ME 2855 Oak Street LLC v. RDR Enterprises, Inc.me-medecided 2022read it at the source ↗
      Show the words that state the rule
      The entry is: Judgment vacated. Remanded to the Superior Court for remand to the District Court for entry of a judgment issuing a writ of possession to 55 Oak Street LLC.
    • statute11 M.R.S. § 2-615enactment date not established
      Show the words that state the rule
      is not a breach of his duty under a contract for sale, if performance as agreed has been made impracticable by the occurrence of a contingency the nonoccurrence of which was a basic assumption on which the contract was made or by compliance in good faith with any applicable foreign or domestic governmental regulation or order whether or not it later proves to be invalid.
    • statute11 M.R.S. § 2-615enactment date not established
      Show the words that state the rule
      Where the causes mentioned in subsection (1) affect only a part of the seller's capacity to perform, he must allocate production and deliveries among his customers but may at his option include regular customers not then under contract as well as his own requirements for further manufacture. He may so allocate in any manner which is fair and reasonable.
    • statute11 M.R.S. § 2-615enactment date not established
      Show the words that state the rule
      The seller must notify the buyer seasonably that there will be delay or nondelivery and, when allocation is required under subsection (2) , of the estimated quota thus made available for the buyer.
    • case2022 ME 2855 Oak Street LLC v. RDR Enterprises, Inc.Me.decided 2022read it at the source ↗
      Show the words that state the rule
      Neither party hereto will be liable for any failure to comply or delay in complying with its obligations hereunder if such failure or delay is, including but not limited to, due to acts of God
    • case2022 ME 2855 Oak Street LLC v. RDR Enterprises, Inc.Me.decided 2022read it at the source ↗
      Show the words that state the rule
      Because we conclude that the District Court erred as a matter of law in interpreting the contract, we need not reach this argument.
    • statute11 M.R.S. § 2-615enactment date not established
      Show the words that state the rule
      Except so far as a seller may have assumed a greater obligation and subject to section 2‑614 on substituted performance (1). Delay in delivery or nondelivery in whole or in part by a seller who complies with subsections (2) and (3) is not a breach of his duty under a contract for sale
    • statute11 M.R.S. § 2-616enactment date not established
      Show the words that state the rule
      Where the buyer receives notification of a material or indefinite delay or an allocation justified under section 2‑615 , he may by written notification to the seller as to any delivery concerned, and where the prospective deficiency substantially impairs the value of the whole contract under the provisions of this Article relating to breach of installment contracts ( section 2‑612 ), then also as to the whole (a). Terminate and thereby discharge any unexecuted portion of the contract; or (b). Modify the contract by agreeing to take his available quota in substitution.
    • statute11 M.R.S. § 2-616enactment date not established
      Show the words that state the rule
      If after receipt of such notification from the seller the buyer fails so to modify the contract within a reasonable time not exceeding 30 days, the contract lapses with respect to any deliveries affected. (3). The provisions of this section may not be negated by agreement except in so far as the seller has assumed a greater obligation under section 2‑615 .
  11. read at the 2026-10-03 bar

    Does a government order or other supervening event excuse performance under this contract?

    Minnesota analyses the question under the Restatement (Second) of Contracts. The Supreme Court held in 2024 that the doctrine of temporary frustration of purpose delineated in Restatement § 269 is a justification for nonperformance recognized under Minnesota law in certain circumstances, and that §§ 265 and 269 are the appropriate frameworks for permanent and temporary frustration respectively. The § 265 test requires the asserting party to prove three elements: that its principal purpose in entering the contract is substantially frustrated, without its fault, by the occurrence of an event the nonoccurrence of which was a basic assumption on which the contract was made; a 'principal purpose' is one so completely the basis of the contract that, as both parties understand, without it the transaction would make little sense. Temporary frustration only SUSPENDS the asserting party's duty rather than discharging remaining duties, and obligations are discharged only if performance afterwards would be 'materially more burdensome', which requires more than inconvenience or increased costs.

    The trap

    The remedy, not the elements, is where this argument usually dies, and a COVID-era closure is the worked example. In Fitness International the tenant could not operate its health club for about 3.5 months under executive orders, and still lost: even assuming the other elements, its rent obligation was merely delayed, and once the closure ended all rent became due. Two limits the opinion states itself. The Court expressly did not decide whether temporary frustration of purpose can support an affirmative breach-of-contract claim rather than only an affirmative defense. And it did NOT construe the lease's own force majeure clause as excusing rent: the clause appears in the opinion's statement of facts, and in footnote 7 the Court treats it as a provision that 'specifically contemplates the risk of “restrictive laws” affecting the contract and allocates that risk to the parties accordingly'. So no sentence here tells you how a Minnesota court reads your force majeure wording; it tells you what the background doctrine gives a party whose clause does not cover the event. What the Restatement text the Court adopted does say is that the discharge applies "unless the language or the circumstances indicate the contrary", so the clause's own words are the first place the doctrine can be switched off.

    as of 2026-09-17

    10 authorities

    • caseMinn. No. A22-1057 (July 24, 2024)Fitness International, LLC v. City Center Ventures, LLCMinn.decided 2024
      Show the words that state the rule
      Expanding on that principle, we hold today that the doctrine of temporary frustration of purpose delineated in the Restatement (Second) of Contracts § 269 is a justification for nonperformance of a contract that is recognized under Minnesota law in certain circumstances. The approaches outlined in Restatement (Second) of Contracts §§ 265, 269 are appropriate frameworks to analyze a claim of permanent or temporary frustration of purpose, respectively.
    • caseMinn. No. A22-1057 (July 24, 2024)Fitness International, LLC v. City Center Ventures, LLCMinn.decided 2024
      Show the words that state the rule
      As set forth in the Restatement, the doctrine of frustration of purpose excuses performance under a contract in certain situations: 8 Where, after a contract is made, a party’s principal purpose is substantially frustrated without his fault by the occurrence of an event the non-occurrence of which was a basic assumption on which the contract was made, his remaining duties to render performance are discharged, unless the language or the circumstances indicate the contrary. Restatement (Second) of Contracts § 265 (Am. L. Inst. 1981). The Restatement approach essentially requires the asserting party to prove three elements: (1) the party’s principal purpose in entering the contract is substantially frustrated; (2) without their fault; (3) by the occurrence of an event, the nonoccurrence of which was a basic assumption on which the contract was made.
    • caseMinn. No. A22-1057 (July 24, 2024)Fitness International, LLC v. City Center Ventures, LLCMinn.decided 2024
      Show the words that state the rule
      A “principal purpose” is one that is “so completely the basis of the contract that, as both parties understand, without it the transaction would make little sense.” Id. at cmt. a. And for a frustration to be “substantial,” it must “be so severe that it is not fairly to be regarded as within the risks that [the asserting party] assumed under the contract.”
    • caseMinn. No. A22-1057 (July 24, 2024)Fitness International, LLC v. City Center Ventures, LLCMinn.decided 2024
      Show the words that state the rule
      Notably, temporary frustration of purpose only suspends the asserting party’s duty, rather than discharging all remaining duties to perform.
    • caseMinn. No. A22-1057 (July 24, 2024)Fitness International, LLC v. City Center Ventures, LLCMinn.decided 2024
      Show the words that state the rule
      Contractual obligations are only discharged if performance would be “materially more burdensome” after the temporary frustration ceases. Id. “Materially more burdensome” performance requires more than inconvenience or increased costs.
    • caseMinn. No. A22-1057 (July 24, 2024)Fitness International, LLC v. City Center Ventures, LLCMinn.decided 2024
      Show the words that state the rule
      For the reasons stated below, we conclude that summary judgment was appropriately granted in favor of City Center. We recognize that the approaches outlined in the Restatement (Second) of Contracts §§ 265, 269 (Am. L. Inst. 1981), are appropriate frameworks to analyze a claim of permanent or temporary frustration of purpose. We have no need to decide, however, whether this permits temporary frustration of purpose to be used as the basis for a breach-of-contract claim and not only as an affirmative defense. Here, even assuming, without deciding, that Fitness was entitled to pursue a claim of temporary frustration of purpose that, if properly supported, would allow it to recover rent paid during the mandatory COVID-19 closure periods, Fitness has not established that its obligation to pay rent owed for the closure periods was discharged, rather than merely suspended. Accordingly, we affirm the decision of the court of appeals, but on different grounds.
    • caseMinn. No. A22-1057 (July 24, 2024)Fitness International, LLC v. City Center Ventures, LLCMinn.decided 2024
      Show the words that state the rule
      For a period of approximately 3.5 months in 2020, however, Fitness was not legally allowed to operate its health club and fitness center due to executive orders mandating closure of certain non-essential businesses to slow the spread of COVID-19.
    • caseMinn. No. A22-1057 (July 24, 2024)Fitness International, LLC v. City Center Ventures, LLCMinn.decided 2024
      Show the words that state the rule
      Fitness’s obligation to pay rent for the closure period was merely delayed by the temporary frustration.
    • caseMinn. No. A22-1057 (July 24, 2024)Fitness International, LLC v. City Center Ventures, LLCMinn.decided 2024
      Show the words that state the rule
      frustration caused by the mandatory closures ended and Fitness was allowed to legally operate its health club and fitness center on the property, all rent payments became due. On these facts, Fitness’s obligation to pay rent for the alleged period of temporary frustration—approximately March to June 2020 and November to December 2020—is not discharged. As a result, Fitness is not entitled to return of the rent payments made to City Center for the mandatory closure periods.
    • caseMinn. No. A22-1057 (July 24, 2024)Fitness International, LLC v. City Center Ventures, LLCMinn.decided 2024
      Show the words that state the rule
      Here, Article XXII of the lease agreement negotiated by Fitness and City Center contains a force majeure clause that specifically contemplates the risk of “restrictive laws” affecting the contract and allocates that risk to the parties accordingly.
  12. read at the 2026-10-03 bar

    Will this force-majeure / impossibility clause excuse late or non-performance, and can the other side draft around it?

    Yes, within limits the statute itself sets, and only ONE of the statutory excuse grounds can be contracted around. Montana codifies contract-excuse doctrine directly in Title 28. The first ground is unwaivable: performance is excused “when such performance or offer is prevented or delayed by the act of the creditor or by the operation of law, even though there may have been a stipulation that this shall not be an excuse” (§ 28-1-1301(1), MCA). Bottrell v. American Bank confirms it operates exactly as written: “performance is excused by one party when it is prevented or delayed by the act of the creditor,” and Smith v. Farmers Union Mutual Insurance applies the same principle to a party that never presented an instrument for payment and then blamed the other side for nonpayment: “the fault for nonperformance (i.e., nonpayment) would lie with FUMIC alone.” The second ground is different in kind: performance is excused “when it is prevented or delayed by an irresistible, superhuman cause or by the act of public enemies of this state or of the United States, unless the parties have expressly agreed to the contrary” (§ 28-1-1301(2), MCA): the classic Act-of-God ground, and the one subsection the parties may narrow or waive by an express contrary agreement. There is a THIRD cause the statute lists and this answer does not turn on: performance is also excused “when the debtor is induced not to make it by any act of the creditor intended or naturally tending to have that effect, done at or before the time at which such performance or offer may be made, and not rescinded before that time” (§ 28-1-1301(3), MCA). Subsection (3) carries no contrary-agreement escape either, so a clause aimed at the Act-of-God ground leaves two of the three causes untouched.

    The trap

    The two grounds are not interchangeable, and a clause that is silent on which one it is aimed at is a real risk. A no-excuse or liquidated-timeline clause drafted broadly enough to reach subsection (2) can validly cut off the Act-of-God excuse: that is what “expressly agreed to the contrary” contemplates. It CANNOT touch subsection (1): no drafting reaches a delay caused by the other party's OWN act or by a change in the law, because the statute excuses that “even though there may have been a stipulation that this shall not be an excuse.” Whether a force-majeure clause's exhaustive list of qualifying events is itself the statute's “express[]…contrary” agreement is not answered by any Montana authority located. The phrase “force majeure” occurs in exactly four published Montana opinions, in no other capitalisation, and none of the four construes subsection (2)'s contrary-agreement proviso, so there is no Montana decision to read on the question.

    as of 2026-09-20

    6 authorities

    • statuteMont. Code Ann. § 28-1-1301enactment date not established
      Show the words that state the rule
      when such performance or offer is prevented or delayed by the act of the creditor or by the operation of law, even though there may have been a stipulation that this shall not be an excuse;
    • statuteMont. Code Ann. § 28-1-1301enactment date not established
      Show the words that state the rule
      when it is prevented or delayed by an irresistible, superhuman cause or by the act of public enemies of this state or of the United States, unless the parties have expressly agreed to the contrary; or
    • case773 P.2d 694Bottrell v. American BankMont.decided 1989read it at the source ↗
      Show the words that state the rule
      Under S 28-1-1301 (1), MCA, performance is excused by one party when it is prevented or delayed by the act of the creditor.
    • statuteMont. Code Ann. § 28-1-1301enactment date not established
      Show the words that state the rule
      The want of performance of an obligation or of an offer of performance, in whole or in part, or any delay therein is excused by the following causes, to the extent to which they operate:
    • statuteMont. Code Ann. § 28-1-1301enactment date not established
      Show the words that state the rule
      when the debtor is induced not to make it by any act of the creditor intended or naturally tending to have that effect, done at or before the time at which such performance or offer may be made, and not rescinded before that time.
    • case2011 MT 216Smith v. Farmers Union Mutual InsuranceMont.decided 2011read it at the source ↗
      Show the words that state the rule
      Because FUMIC did not even attempt to present the order for payment, the fault for nonperformance (i.e., nonpayment) would lie with FUMIC alone. In that instance, FUMIC could not fault the Smiths for nonpayment
  13. read at the 2026-10-03 bar

    Will this force-majeure clause excuse our performance in Nebraska?

    No authority located answers that, and the finding is the answer: there is no Nebraska force-majeure statute for a private contract and no Nebraska appellate decision construing a force-majeure CLAUSE. What Nebraska does have is the doctrine behind the clause, and it is strict. Armstrong v. Clarkson College states it: “The doctrine of impossibility of performance, often now called impracticability of performance, excuses a promi- sor's failure to perform a duty under a contract where perform­ ance has been rendered severely impracticable or impossible by unforeseen circumstances”, on Restatement (Second) of Contracts § 261, “Where, after a contract is made, a party's performance is made impracticable without his fault by the occurrence of an event the non-occurrence of which was a basic assumption on which the contract was made, his duty to render that performance is discharged, unless the lan- guage or the circumstances indicate the contrary.” The three requirements are set out in the same opinion: “(1) the occurrence (or nonoccurrence) of the event causing the impracticability was unexpected; (2) performance of the duty by the promisor would be extremely difficult and burdensome, if not impossi- ble; and (3) the promisor did not assume the risk of the event's occurrence (or nonoccurrence).” Two further limits decide cases. Hardship is not enough: “Performance of a contractual duty is not impracticable merely because it has become inconvenient or more expen- sive.35 Mere difficulty of performance is not enough.” And the party invoking it carries an affirmative burden: “the party invoking the impracticability defense must show that he or she used reasonable efforts to surmount the obstacles which prevented performance.” Cleasby v. Leo A. Daly Co. gives the doctrine's other names in Nebraska: “Business necessity is sometimes called impossibility of performance, extreme impracticability, frustration of contract, or implied condition in the promise.”

    The trap

    Foreseeability is the Nebraska tripwire, and it is applied at a high level of generality. Armstrong refused an impossibility instruction because “it was not unexpected that a student might be placed on probation or that a clinical site might dismiss or refuse to accept a student”, even though “the specific details of Armstrong's behavior might have been unexpected”. If the CATEGORY of event was foreseeable, the specific instance being a surprise does not help. Second trap: you have to have tried. “Clarkson's instruction was not warranted, because the difficulty was not unexpected and Clarkson failed to take reasonable steps to overcome the difficulty”, so a party that invokes the clause without documenting what it did to perform anyway is arguing a defence it has not made out. Third, and this is where this rule is honest with you: because NO Nebraska opinion construes a force-majeure clause, nothing here tells you how a Nebraska court will read the words you drafted, whether a catch-all sweeps in an unlisted event, whether notice is a condition, who bears the burden under the clause as opposed to the doctrine, or whether the clause displaces the common law at all. One decision has touched such a clause without construing one: Blue Creek Farm v. Aurora Cooperative Elevator Co. defined the device: “In general, a force majeure provision is a contractual provision that allocates the risk if performance becomes impossible or impracticable as a result of an event or effect that the parties could not have anticipated or controlled.”, and then decided only whether invoking it was a repudiation, holding it was not clearly erroneous to find that a buyer who gave notice of a 30-day delay had not repudiated. Nothing in it reads a trigger, a catch-all or a notice condition. Fourth, a statutory false friend: the ONLY Nebraska section containing the phrase “force majeure” is Neb. Rev. Stat. § 8-3104 in the LIBOR Transition Act, and it points the other way. A benchmark discontinuance shall not “[h]ave the effect of (i) discharging or excusing performance under any contract, security, or instrument for any reason, claim, or defense, including, but not limited to, any force majeure or other provision in any contract, security, or instrument”. Citing it as Nebraska's force-majeure statute would be a serious error. Fifth, one doctrine you may expect and will not find stated by a court you can cite: “frustration of purpose” is named in exactly one Nebraska opinion we hold, a 2024 Court of Appeals memorandum web opinion that is not designated for permanent publication and may not be cited except as its own notice provides, and no Nebraska Supreme Court opinion uses the phrase at all.

    as of 2026-09-20

    12 authorities

    • case901 N.W.2d 1Armstrong v. Clarkson CollegeNeb.decided 2017read it at the source ↗
      Show the words that state the rule
      The doctrine of impossibility of performance, often now called impracticability of performance, excuses a promi- sor’s failure to perform a duty under a contract where perform­ ance has been rendered severely impracticable or impossible by unforeseen circumstances
    • case901 N.W.2d 1Armstrong v. Clarkson CollegeNeb.decided 2017read it at the source ↗
      Show the words that state the rule
      Where, after a contract is made, a party’s performance is made impracticable without his fault by the occurrence of an event the non-occurrence of which was a basic assumption on which the contract was made, his duty to render that performance is discharged, unless the lan- guage or the circumstances indicate the contrary.
    • case901 N.W.2d 1Armstrong v. Clarkson CollegeNeb.decided 2017read it at the source ↗
      Show the words that state the rule
      There are three general requirements for the application of the doctrine of impracticability of performance: (1) the occurrence (or nonoccurrence) of the event causing the impracticability was unexpected; (2) performance of the duty by the promisor would be extremely difficult and burdensome, if not impossi- ble; and (3) the promisor did not assume the risk of the event’s occurrence (or nonoccurrence).
    • case901 N.W.2d 1Armstrong v. Clarkson CollegeNeb.decided 2017read it at the source ↗
      Show the words that state the rule
      Performance of a contractual duty is not impracticable merely because it has become inconvenient or more expen- sive.35 Mere difficulty of performance is not enough.
    • case901 N.W.2d 1Armstrong v. Clarkson CollegeNeb.decided 2017read it at the source ↗
      Show the words that state the rule
      And the party invoking the impracticability defense must show that he or she used reasonable efforts to surmount the obstacles which prevented performance.
    • case901 N.W.2d 1Armstrong v. Clarkson CollegeNeb.decided 2017read it at the source ↗
      Show the words that state the rule
      Clarkson’s instruction was not warranted, because the difficulty was not unexpected and Clarkson failed to take reasonable steps to overcome the difficulty.
    • case901 N.W.2d 1Armstrong v. Clarkson CollegeNeb.decided 2017read it at the source ↗
      Show the words that state the rule
      Here, it was not unexpected that a student might be placed on probation or that a clinical site might dismiss or refuse to accept a student. While the specific details of Armstrong’s behavior might have been unexpected, it certainly was not unforeseen to Clarkson that a student might act in an unprofessional manner.
    • case376 N.W.2d 312Cleasby v. Leo A. Daly Co.Neb.decided 1985read it at the source ↗
      Show the words that state the rule
      Business necessity is sometimes called impossibility of performance, extreme impracticability, frustration of contract, or implied condition in the promise.
    • statuteNeb. Rev. Stat. § 8-3104enactment date not established
      Show the words that state the rule
      Any LIBOR discontinuance event or LIBOR replacement date, selection or use of a recommended benchmark replacement as a benchmark replacement, or determination, implementation, or performance of benchmark replacement conforming changes that occurs by operation of section 8-3103 shall not: (a) Be deemed to impair or affect the right of any person to receive a payment, or affect the amount or timing of such payment, under any contract, security, or instrument; or (b) Have the effect of (i) discharging or excusing performance under any contract, security, or instrument for any reason, claim, or defense, including, but not limited to, any force majeure or other provision in any contract, security, or instrument, (ii) giving any person the right to unilaterally terminate or suspend performance under any contract, security, or instrument, (iii) constituting a breach of a contract, security, or instrument, or (iv) voiding or nullifying any contract, security, or instrument.
    • case901 N.W.2d 1Armstrong v. Clarkson CollegeNeb.decided 2017read it at the source ↗
      Show the words that state the rule
      The Restatement (Second) on Contracts, § 261, entitled “Discharge by Supervening Impracticability,” states:
    • case614 N.W.2d 310Blue Creek Farm, Inc. v. Aurora Cooperative Elevator Co.Neb.decided 2000read it at the source ↗
      Show the words that state the rule
      In general, a force majeure provision is a contractual provision that allocates the risk if performance becomes impossible or impracticable as a result of an event or effect that the parties could not have anticipated or controlled.
    • case614 N.W.2d 310Blue Creek Farm, Inc. v. Aurora Cooperative Elevator Co.Neb.decided 2000read it at the source ↗
      Show the words that state the rule
      We conclude that the district court was not clearly erroneous in finding that Aurora did not repudiate the contracts by sending the letter informing Blue Creek that it intended to delay performance by 30 days.
  14. read at the 2026-10-03 bar

    Does New Jersey excuse performance when the force majeure event hits?

    For a sale of goods, yes on the statutory terms: delay in delivery or non-delivery by a seller who complies with the allocation and notice paragraphs is not a breach if performance as agreed has been made impracticable by the occurrence of a contingency the non-occurrence of which was a basic assumption on which the contract was made, or by good-faith compliance with any applicable foreign or domestic governmental regulation or order, whether or not it later proves invalid. Excuse is conditional: where the contingency affects only part of the seller's capacity, the seller must allocate production and deliveries among customers in a fair and reasonable manner, and must seasonably notify the buyer of the delay or non-delivery and of any quota. The section is also "subject to the preceding section on substituted performance": where agreed facilities or carriers fail or the agreed manner of delivery becomes commercially impracticable but a commercially reasonable substitute is available, "such substitute performance must be tendered and accepted" (§ 12A:2-614(1)). And the buyer has the next move: on notice of a material or indefinite delay or an allocation, the buyer may by written notice terminate the unexecuted portion or take its quota in substitution; if the buyer does not modify within a reasonable time not exceeding thirty days, the contract lapses as to the affected deliveries; and that section "may not be negated by agreement" except where the seller has assumed a greater obligation (§ 12A:2-616).

    The trap

    Two things follow that drafters miss. First, § 12A:2-615 opens 'Except so far as a seller may have assumed a greater obligation'. A contractual guarantee of supply displaces the statutory excuse, so to the extent the seller has assumed a greater obligation the statutory excuse yields to it; whether a given delivery warranty is such an assumption is not resolved by any New Jersey authority we hold. Second, the excuse comes with duties: a seller who stops shipping without allocating fairly among customers, or without seasonable notice, loses it. Note this rule states the GOODS rule only. We could not verify a New Jersey Supreme Court force-majeure or common-law impracticability rule for services or leases: a full-text scan of every New Jersey Supreme Court opinion checked for this rule found the phrase 'force majeure' in none.

    as of 2026-09-16

    5 authorities

    • statuteN.J. Stat. Ann. § 12A:2-615enactment date not established
      Show the words that state the rule
      (a) Delay in delivery or non-delivery in whole or in part by a seller who complies with paragraphs (b) and (c) is not a breach of his duty under a contract for sale if performance as agreed has been made impracticable by the occurrence of a contingency the non-occurrence of which was a basic assumption on which the contract was made or by compliance in good faith with any applicable foreign or domestic governmental regulation or order whether or not it later proves to be invalid.
    • statuteN.J. Stat. Ann. § 12A:2-615enactment date not established
      Show the words that state the rule
      Except so far as a seller may have assumed a greater obligation and subject to the preceding section on substituted performance:
    • statuteN.J. Stat. Ann. § 12A:2-615enactment date not established
      Show the words that state the rule
      (b) Where the causes mentioned in paragraph (a) affect only a part of the seller's capacity to perform, he must allocate production and deliveries among his customers but may at his option include regular customers not then under contract as well as his own requirements for further manufacture. He may so allocate in any manner which is fair and reasonable. (c) The seller must notify the buyer seasonably that there will be delay or non-delivery and, when allocation is required under paragraph (b), of the estimated quota thus made available for the buyer.
    • statuteN.J. Stat. Ann. § 12A:2-614enactment date not established
      Show the words that state the rule
      (1) Where without fault of either party the agreed berthing, loading, or unloading facilities fail or an agreed type of carrier becomes unavailable or the agreed manner of delivery otherwise becomes commercially impracticable but a commercially reasonable substitute is available, such substitute performance must be tendered and accepted. (2) If the agreed means or manner of payment fails because of domestic or foreign governmental regulation, the seller may withhold or stop delivery unless the buyer provides a means or manner of payment which is commercially a substantial equivalent. If delivery has already been taken, payment by the means or in the manner provided by the regulation discharges the buyer's obligation unless the regulation is discriminatory, oppressive or predatory.
    • statuteN.J. Stat. Ann. § 12A:2-616enactment date not established
      Show the words that state the rule
      (1) Where the buyer receives notification of a material or indefinite delay or an allocation justified under the preceding section he may by written notification to the seller as to any delivery concerned, and where the prospective deficiency substantially impairs the value of the whole contract under the provisions of this Chapter relating to breach of installment contracts (12A:2-612), then also as to the whole, (a) terminate and thereby discharge any unexecuted portion of the contract; or (b) modify the contract by agreeing to take his available quota in substitution. (2) If after receipt of such notification from the seller the buyer fails so to modify the contract within a reasonable time not exceeding thirty days the contract lapses with respect to any deliveries affected. (3) The provisions of this section may not be negated by agreement except in so far as the seller has assumed a greater obligation under the preceding section.
  15. read at the 2026-10-03 bar

    Will this force majeure clause excuse our performance when something unexpected stops us?

    Only if the clause names the event. New York reads force majeure clauses, clauses excusing nonperformance due to circumstances beyond the parties' control, as a narrow defence: ordinarily only if the clause specifically includes the event that actually prevented performance will the party be excused. A catch-all such as 'or other similar causes beyond the control of such party' does not enlarge it: the general words are not given expansive meaning and are confined to things of the same kind or nature as the particular matters mentioned. The common-law impossibility defence is no wider: it requires destruction of the subject matter or the means of performance, produced by an unanticipated event that could not have been foreseen or guarded against in the contract.

    The trap

    The New York trap is the risk-allocation logic behind the narrowness: if the party could have foreseen and guarded against the event when it undertook the obligation, neither the clause nor impossibility helps. In Kel Kim (a unanimous memorandum of the Court of Appeals, affirming with costs after Special Term nullified the lease and directed the tenant to vacate and a divided Appellate Division affirmed), the tenant's inability to renew liability insurance during an insurance-market crisis was held outside both doctrines: the lease required it to 'procure and maintain in full force and effect a public liability insurance policy', and the Court held that that inability 'could have been foreseen and guarded against when it specifically undertook that obligation in the lease, and therefore the obligation cannot be excused on this basis'. The listed events in that clause: labour disputes, inability to procure materials, utility failure, restrictive governmental laws or regulations, riots, insurrection, war, adverse weather, Acts of God: are quoted from the lease itself, and the Court held that they 'are different in kind and nature from Kel Kim's inability to procure and maintain public liability insurance' because 'The recited events pertain to a party's ability to conduct day-to-day commercial operations on the premises.' The tenant argued that the same could be said of maintaining insurance, and lost: the Court held such an event 'materially different', because an always-maintain-insurance covenant goes 'not to frustrated expectations in day-to-day commercial operations on the premises -- such as interruptions in the availability of labor, materials and utility services -- but to the bargained-for protection of the landlord's unrelated economic interests'. That is how tightly the ejusdem generis limit binds. Drafting consequence: name pandemics, supply-chain failure, cyber events and government shutdowns expressly, and say the catch-all is not limited to the enumerated kinds.

    as of 2026-09-16

    9 authorities

    • case70 N.Y.2d 900Kel Kim Corp. v. Central Markets, Inc.N.Y.decided 1987read it at the source ↗
      Show the words that state the rule
      For much the same underlying reason, contractual force majeure clauses — or clauses excusing nonperformance due to circumstances beyond the control of the parties — under the common law provide a similarly narrow defense. Ordinarily, only if the force majeure clause specifically includes the event that actually prevents a party’s performance will that party *903 be excused.
    • case70 N.Y.2d 900Kel Kim Corp. v. Central Markets, Inc.N.Y.decided 1987read it at the source ↗
      Show the words that state the rule
      The principle of interpretation applicable to such clauses is that the general words are not to be given expansive meaning; they are confined to things of the same kind or nature as the particular matters mentioned
    • case70 N.Y.2d 900Kel Kim Corp. v. Central Markets, Inc.N.Y.decided 1987read it at the source ↗
      Show the words that state the rule
      While such defenses have been recognized in the common law, they have been applied narrowly, due in part to judicial recognition that the purpose of contract law is to allocate the risks that might affect performance and that performance should be excused only in extreme circumstances (see, Wallach, The Excuse Defense in the Law of Contracts: Judicial Frustration of the U.C.C. Attempt to Liberalize the Law of Commercial Impracticability, 55 Notre Dame Law 203, 207 [1979]). Impossibility excuses a party’s performance only when the destruction of the subject matter of the contract or the means of performance makes performance objectively impossible. Moreover, the impossibility must be produced by an unanticipated event that could not have been foreseen or guarded against in the contract
    • case70 N.Y.2d 900Kel Kim Corp. v. Central Markets, Inc.decided 1987read it at the source ↗
      Show the words that state the rule
      Here, of course, the contractual provision does not specifically include plaintiffs inability to procure and maintain insurance. Nor does this inability fall within the catchall "or other similar causes beyond the control of such party.”
    • case70 N.Y.2d 900Kel Kim Corp. v. Central Markets, Inc.N.Y.decided 1987read it at the source ↗
      Show the words that state the rule
      The clause reads: "If either party to this Lease shall be delayed or prevented from the performance of any obligation through no fault of their own by reason of labor disputes, inability to procure materials, failure of utility service, restrictive governmental laws or regulations, riots, insurrection, war, adverse weather, Acts of God, or other similar causes beyond the control of such party, the performance of such obligation shall be excused for the period of the delay.”
    • case70 N.Y.2d 900Kel Kim Corp. v. Central Markets, Inc.N.Y.decided 1987read it at the source ↗
      Show the words that state the rule
      The lease required Kel Kim to "procure and maintain in full force and effect a public liability insurance policy or policies in a solvent and responsible company or companies * * * of not less than Five Hundred Thousand Dollars * * * to any single person and in the aggregate of not less than One Million Dollars * * * on account of any single accident”.
    • case70 N.Y.2d 900Kel Kim Corp. v. Central Markets, Inc.N.Y.decided 1987read it at the source ↗
      Show the words that state the rule
      Special Term granted defendants’ motion for summary judgment, nullified the lease, and directed Kel Kim to vacate the premises. A divided Appellate Division affirmed.
    • case70 N.Y.2d 900Kel Kim Corp. v. Central Markets, Inc.N.Y.decided 1987read it at the source ↗
      Show the words that state the rule
      Applying these principles, we conclude that plaintiff’s predicament is not within the embrace of the doctrine of impossibility. Kel Kim’s inability to procure and maintain requisite coverage could have been foreseen and guarded against when it specifically undertook that obligation in the lease, and therefore the obligation cannot be excused on this basis.
    • case70 N.Y.2d 900Kel Kim Corp. v. Central Markets, Inc.N.Y.decided 1987read it at the source ↗
      Show the words that state the rule
      We agree with the conclusion reached by the majority below that the events listed in the force majeure clause here are different in kind and nature from Kel Kim’s inability to procure and maintain public liability insurance. The recited events pertain to a party’s ability to conduct day-to-day commercial operations on the premises. While Kel Kim urges that the same may be said of a failure to procure and maintain insurance, such an event is materially different. The requirement that specified amounts of public liability insurance at all times be maintained goes not to frustrated expectations in day-to-day commercial operations on the premises — such as interruptions in the availability of labor, materials and utility services — but to the bargained-for protection of the landlord’s unrelated economic interests where the tenant chooses to continue operating a public roller skating rink on the premises. Chief Judge Wachtler and Judges Simons, Kaye, Alexander, Titone, Hancock, Jr., and Bellacosa concur. Order affirmed, with costs, in a memorandum.
  16. read at the 2026-10-03 bar

    Will this force majeure clause excuse our performance in North Carolina?

    No North Carolina opinion construing a force majeure clause was found, so what follows is the background doctrine such a clause is drafted against and not an answer for the clause itself. In Brenner the Supreme Court of North Carolina stated that 'impossibility of performance is recognized in this jurisdiction as excusing a party from performing under an executory contract if the subject matter of the contract is destroyed without fault of the party seeking to be excused from performance' (a narrow rule keyed to destruction of the subject matter, not to hardship), and held it had 'no bearing' on the case before it because the promised performance remained possible. The same opinion sets out two limits on frustration of purpose, stated on the authority of the treatise it cites and then applied as the ground of decision: 'if the frustrating event was reasonably foreseeable, the doctrine of frustration is not a defense', and 'if the parties have contracted in reference to the allocation of the risk involved in the frustrating event, they may not invoke the doctrine of frustration to escape their obligations'. The Court applied the second to a tuition term reading 'payable in advance of the first day of school, no portion refundable' and held that the term allocated to the payor the risk that the child would not attend and so prevented the doctrine. For a sale of goods there is a statutory excuse with its own conditions: N.C.G.S. § 25-2-615 opens 'Except so far as a seller may have assumed a greater obligation and subject to the preceding section [G.S. 25-2-614] on substituted performance', and subdivision (1) then provides that delay in delivery or non-delivery by a seller who complies with subdivisions (2) and (3) is not a breach of the seller's duty if performance as agreed has been made impracticable by the occurrence of a contingency the non-occurrence of which was a basic assumption on which the contract was made, or by good-faith compliance with any applicable foreign or domestic governmental regulation or order whether or not it later proves invalid.

    The trap

    The § 25-2-615 excuse is conditional on two duties the clause usually omits. Where the contingency affects only part of the seller's capacity, subdivision (2) requires the seller to ALLOCATE production and deliveries among its customers, and it may so allocate 'in any manner which is fair and reasonable'; subdivision (3) requires the seller to notify the buyer seasonably of the delay or non-delivery and, where allocation is required, of the buyer's estimated quota. A seller that does neither is outside the section on its own words, because subdivision (1) excuses only a seller 'who complies with subdivisions (2) and (3)'. The section also runs in one direction only (it excuses a SELLER), and it yields to a greater obligation the seller has assumed, which is what a broadly drafted force-majeure clause may be. Then the harder point, which cuts the other way: Brenner holds that where the parties have contracted about the allocation of the risk of the frustrating event they may not invoke frustration of purpose, and it enforced a one-line 'no portion refundable' term as exactly that allocation. The clause you draft is therefore as likely to be read as the parties' allocation of the risk of the event as it is to be read as an excuse from it, and on Brenner's reasoning a clause that names an event and states its consequence may be read as having allocated that risk. Brenner also held that hardship short of destruction did not excuse: the payor 'did not receive the full consideration contemplated by the contract' yet received enough to defeat the doctrine, and 'there was no substantial destruction of the value of the contract'. Two reservations remain. Brenner reached frustration of purpose by agreeing with a Court of Appeals dissent's general discussion of the law and then applying the doctrine's own limits to reject it on the facts; it did not squarely announce frustration of purpose as a North Carolina doctrine, and its long exposition of the doctrine is quoted from a legal encyclopaedia, not worked out by the Court. And whether a North Carolina court will read a force majeure clause to reach an event the clause does not name was not answered by anything read here.

    as of 2026-09-17

    10 authorities

    • case302 N.C. 207Brenner v. Little Red School House, Ltd.N.C.decided 1981read it at the source ↗
      Show the words that state the rule
      Impossibility of performance is recognized in this jurisdiction as excusing a party from performing under an executory contract if the subject matter of the contract is destroyed without fault of the party seeking to be excused from performance.
    • case302 N.C. 207Brenner v. Little Red School House, Ltd.N.C.decided 1981read it at the source ↗
      Show the words that state the rule
      Plaintiff’s former wife’s refusal to send the child to defendant school did not destroy the subject matter of the contract; it was still possible for the child to attend the school. The doctrine of impossibility of performance clearly has no bearing on this case.
    • statuteN.C.G.S. § 25-2-615enactment date not established
      Show the words that state the rule
      Except so far as a seller may have assumed a greater obligation and subject to the preceding section [G.S. 25-2-614] on substituted performance: (1) Delay in delivery or nondelivery in whole or in part by a seller who complies with subdivisions (2) and (3) [of this section] is not a breach of his duty under a contract for sale if performance as agreed has been made impracticable by the occurrence of a contingency the nonoccurrence of which was a basic assumption on which the contract was made or by compliance in good faith with any applicable foreign or domestic governmental regulation or order whether or not it later proves to be invalid.
    • case302 N.C. 207Brenner v. Little Red School House, Ltd.N.C.decided 1981read it at the source ↗
      Show the words that state the rule
      While we agree with Judge Martin’s general discussion of the law concerning frustration of purpose, we hold that the doctrine does not apply to bring about a recission under the facts of this case.
    • case302 N.C. 207Brenner v. Little Red School House, Ltd.N.C.decided 1981read it at the source ↗
      Show the words that state the rule
      If the frustrating event was reasonably foreseeable, the doctrine of frustration is not a defense. In addition, if the parties have contracted in reference to the allocation of the risk involved in the frustrating event, they may not invoke the doctrine of frustration to escape their obligations.
    • case302 N.C. 207Brenner v. Little Red School House, Ltd.N.C.decided 1981read it at the source ↗
      Show the words that state the rule
      Therefore, although plaintiff did not receive the full consideration contemplated by the contract, he received consideration sufficient to avoid the application of the doctrine of frustration of purpose. There was no substantial destruction of the value of the contract.
    • case302 N.C. 207Brenner v. Little Red School House, Ltd.N.C.decided 1981read it at the source ↗
      Show the words that state the rule
      Furthermore, we find the doctrine of frustration of purpose inapplicable on an additional basis. Although the parties could not have been expected to forsee the exact actions of plaintiffs former wife in refusing to send the child to defendant school, the possibility that the child might not attend was foreseeable and appears expressly provided for in the contract. The contract states that tuition is “payable in advance of the first day of school, no portion refundable.” This provision allocates to plaintiff the risk that the child will not attend, and prevents the application of the doctrine of frustration of purpose.
    • case302 N.C. 207Brenner v. Little Red School House, Ltd.N.C.decided 1981read it at the source ↗
      Show the words that state the rule
      For the reasons stated, we reverse the decision of the Court of Appeals and remand to that court with instructions to remand to the District Court, Guilford County, for a New trial.
    • statuteN.C.G.S. § 25-2-615enactment date not established
      Show the words that state the rule
      (2) Where the causes mentioned in subdivision (1) [of this section] affect only a part of the seller's capacity to perform, he must allocate production and deliveries among his customers but may at his option include regular customers not then under contract as well as his own requirements for further manufacture. He may so allocate in any manner which is fair and reasonable.
    • statuteN.C.G.S. § 25-2-615enactment date not established
      Show the words that state the rule
      (3) The seller must notify the buyer seasonably that there will be delay or nondelivery and, when allocation is required under subdivision (2) [of this section], of the estimated quota thus made available for the buyer.
  17. read at the 2026-10-03 bar

    Can our counterparty walk away because an outside event, or a government decision, wrecked the deal?

    Not on the strength of frustration of purpose alone, on the Ohio authority verified here. The Eleventh District recorded in 2021 that 'The Supreme Court of Ohio has not expressly adopted the doctrine of frustration of purpose', and declined to adopt it in that case (Wroblesky). The related excuse of impracticability due to government action fails where the contract itself put that risk on the party seeking excuse: because the parties expressly allocated the risk of government delay to the appellants, the court held the doctrine precluded. Two Supreme Court of Ohio statements, quoted in that decision, set the standard and are the harder obstacle. Ordinarily, where one contracts to render a performance for which a government licence or permit is required, it is that party's duty to get the licence, the risk of inability to obtain it is on that party, and refusal by the government is no defence to a breach claim; and governmental interference cannot excuse performance unless it truly supervenes in a way beyond the seller's assumption of risk, the contingency having to be unforeseen and unusual (Security Sewage, as Wroblesky quotes it).

    The trap

    That makes the allocation language in the clause, not the size of the outside event, the thing that decides an Ohio case. A tenant whose whole purpose depended on a state licence still had to pay, because the lease did not make the licence a condition precedent and did allocate the delay risk. Two limits on this rule, stated rather than glossed over: Wroblesky is a Court of Appeals decision and binds only the Eleventh District, and it is a statement that the Supreme Court has not expressly adopted the doctrine, not a holding that no Ohio court will ever apply it. The impracticability standard stated above is drawn from Official Comment 10 to Ohio's sale-of-goods excuse provision, R.C. 1302.73, by way of a 1968 Supreme Court of Ohio decision; the words of the section itself are not quoted in any authority listed here, so nothing in this rule states the elements of the statutory excuse for a contract for the sale of goods.

    as of 2026-09-17

    8 authorities

    • case2021-Ohio-1063Wroblesky v. HughleyOhio Ct. App. 11th Dist.decided 2021
      Show the words that state the rule
      The Supreme Court of Ohio has not expressly adopted the doctrine of frustration of purpose, and we decline to do so in the present case. Even if the defense were available, however, the appellants did not raise genuine issues of material fact regarding its applicability.
    • case2021-Ohio-1063Wroblesky v. HughleyOhio Ct. App. 11th Dist.decided 2021
      Show the words that state the rule
      Since the parties expressly allocated the risk of government delay to the appellants, the doctrine of impracticability due to government action is precluded.
    • case2021-Ohio-1063Wroblesky v. HughleyOhio Ct. App. 11th Dist.decided 2021
      Show the words that state the rule
      whether the issuance of a liquor permit to the appellants was a condition precedent to the Wrobleskys’ enforcement of the lease; (2) whether the appellants’ performance was excused because of frustration of purpose; and (3) whether the appellants’ performance was excused because of impracticability due to government action. {¶3} After a careful review of the record and pertinent law, we find as follows: {¶4} (1) Based on the plain and ordinary meaning of the lease, the parties did not intend the issuance of a liquor permit to be a condition precedent to the appellants’ payment obligations.
    • case2021-Ohio-1063Wroblesky v. HughleyOhio Ct. App. 11th Dist.decided 2021
      Show the words that state the rule
      Further, the Supreme Court of Ohio has held that “‘[o]rdinarily, when one contracts to render a performance for which a government license or permit is required, it is his duty to get the license or permit so that he can perform. The risk of inability to obtain it is on him; and its refusal by the government is no defense in a suit for breach of his contract.’” Security Sewage Equip. Co. v. McFerren, 14 Ohio St.2d 251, 254, 237 N.E.2d 898 (1968), quoting 6 Corbin on Contracts, Section 1347, at 435.
    • case2021-Ohio-1063Wroblesky v. HughleyOhio Ct. App. 11th Dist.decided 2021
      Show the words that state the rule
      The Supreme Court of Ohio has held that “‘governmental interference cannot excuse [performance] unless it truly “supervenes” in such a manner as to be beyond the seller’s assumption of risk.’ In order to excuse performance, the contingency must be unforeseen and unusual.” Security Sewage at 254, quoting R.C. 1302.73, Comment 10.
    • case2021-Ohio-1063Wroblesky v. HughleyOhio Ct. App. 11th Dist.decided 2021
      Show the words that state the rule
      As indicated, the lease required the appellants to obtain the licenses or permits necessary to conduct their business operations. The lease did not excuse the appellants’ payment obligation in the event of “restrictive governmental laws or regulations, * * * or other reason beyond its control.” Based on the plain and ordinary 15 meaning of these provisions, the parties expressly allocated the risk of government delay to the appellants.
    • case2021-Ohio-1063Wroblesky v. HughleyOhio Ct. App. 11th Dist.decided 2021
      Show the words that state the rule
      The Supreme Court of Ohio has not expressly adopted the doctrine, although the court once acknowledged its existence in a footnote. See In re Adams, 45 Ohio St.3d 219, 220, 543 N.E.2d 797 (1989), fn. 1 (“With respect to the separation agreement, appellee does not challenge the enforceability of the agreement by asserting claims based upon the law of contracts, to wit: frustration of purpose, impossibility of performance or conditions subsequent. Our review of the record discloses no facts to support such assertions”).
    • case2021-Ohio-1063Wroblesky v. HughleyOhio Ct. App. 11th Dist.decided 2021
      Show the words that state the rule
      Ohio courts that have recognized the doctrine have adopted the standard set forth in the Restatement of the Law. See, e.g., Donald Harris Law Firm at ¶ 16.3 The Restatement describes “discharge by supervening frustration” as follows: {¶58} “Where, after a contract is made, a party’s principal purpose is substantially frustrated without his fault by the occurrence of an event, the non-occurrence of which was a basic assumption on which the contract was made, his remaining duties to render performance are discharged, unless the language or the circumstances indicate the contrary.” Restatement of the Law 2d, Contracts, Section 265, at 334 (1981).
  18. read at the 2026-10-03 bar

    Does Oregon excuse performance when the event the clause was meant to cover happens, or when the contract has no force majeure clause?

    Oregon has no general force majeure statute; what it has is a default excuse rule for sales of goods and an older common-law doctrine. For goods, except so far as a seller has assumed a greater obligation and subject to ORS 72.6140 on substituted performance, delay in delivery or nondelivery in whole or in part by a seller who complies with ORS 72.6150(2) and (3) is not a breach if performance as agreed has been made impracticable by the occurrence of a contingency the nonoccurrence of which was a basic assumption on which the contract was made, or by good-faith compliance with an applicable foreign or domestic governmental regulation or order whether or not it later proves invalid; a seller so affected in part must allocate production and deliveries fairly and reasonably among customers, and must notify the buyer seasonably of the delay, nondelivery or quota (72.6150). Where the agreed berthing, loading or unloading facilities fail, the agreed carrier becomes unavailable, or the agreed manner of delivery otherwise becomes commercially impracticable, a commercially reasonable substitute must be tendered and accepted (72.6140(1)); and where the agreed means or manner of payment fails because of a governmental regulation, the seller may withhold or stop delivery unless the buyer provides a commercially substantially equivalent means or manner of payment, while payment in the manner the regulation provides discharges a buyer that has already taken delivery unless the regulation is discriminatory, oppressive or predatory (72.6140(2)). On notice of a material or indefinite delay or an allocation, the buyer may terminate the unexecuted portion or take the available quota in substitution (72.6160(1)), and 72.6160's provisions may not be negated by agreement except so far as the seller has assumed a greater obligation under 72.6150. A buyer that does nothing loses the choice: if the buyer does not modify the contract within a reasonable time not exceeding 30 days after the seller's notification, the contract lapses as to any deliveries affected (72.6160(2)). Outside the sale of goods, the Oregon Supreme Court has stated the doctrine of supervening impossibility of performance: where the parties contract on the assumption that some particular thing necessary to performance will continue to exist and be available, and neither agrees to be responsible for its continued existence and availability, the contract is subject to the implied condition that if that thing ceases to exist or be available before the time for performance, without the default of either party, the contract is dissolved and the parties excused. That doctrine is stated as an exception: the common-law starting point the court gave is that a tenant remains liable for the agreed rent so long as any part of the premises remains in existence capable of being occupied or enjoyed, irrespective of injury or destruction by fire or other casualty. Applying the authorities it had set out to the lease before it, the court found that the destruction of the buildings and service station equipment by fire worked a termination of the original lease and the sublease, so the landlord was lawfully entitled to possession (Eggen v. Wetterborg, 1951).

    The trap

    In a sale of goods the seller's excuse is conditioned on performing 72.6150(2) and (3): a seller who does not allocate fairly among customers, or does not give the buyer seasonable notice of the delay, nondelivery or quota, is outside the section. The doctrine stated in Eggen turns on the parties not having allocated the risk: it applies only where neither party agreed to be responsible for the thing's continued existence and availability, so a clause that assigns that risk displaces it, and the common-law rule the court stated runs the other way, leaving a tenant liable for rent despite destruction by fire so long as any part of the premises can still be occupied or enjoyed. Nothing quoted in this rule states how an express force majeure clause is construed in Oregon, or whether commercial impracticability excuses performance outside a sale of goods.

    as of 2026-09-17

    11 authorities

    • statuteORS 72.6150enactment date not established
      Show the words that state the rule
      Except so far as a seller may have assumed a greater obligation and subject to the preceding section on substituted performance: (1) Delay in delivery or nondelivery in whole or in part by a seller who complies with subsections (2) and (3) of this section is not a breach of duty under a contract for sale if performance as agreed has been made impracticable by the occurrence of a contingency the nonoccurrence of which was a basic assumption on which the contract was made or by compliance in good faith with any applicable foreign or domestic governmental regulation or order whether or not it later proves to be invalid.
    • statuteORS 72.6150enactment date not established
      Show the words that state the rule
      Where the causes mentioned in subsection (1) of this section affect only a part of the seller’s capacity to perform, the seller must allocate production and deliveries among customers but may at the option of the seller include regular customers not then under contract as well as the requirements of the seller for further manufacture. The seller may so allocate in any manner which is fair and reasonable.
    • statuteORS 72.6150enactment date not established
      Show the words that state the rule
      The seller must notify the buyer seasonably that there will be delay or nondelivery and, when allocation is required under subsection (2) of this section, of the estimated quota thus made available for the buyer.
    • statuteORS 72.6140enactment date not established
      Show the words that state the rule
      Where without fault of either party the agreed berthing, loading, or unloading facilities fail or an agreed type of carrier becomes unavailable or the agreed manner of delivery otherwise becomes commercially impracticable but a commercially reasonable substitute is available, such substitute performance must be tendered and accepted.
    • statuteORS 72.6140enactment date not established
      Show the words that state the rule
      If the agreed means or manner of payment fails because of domestic or foreign governmental regulation, the seller may withhold or stop delivery unless the buyer provides a means or manner of payment which is commercially a substantial equivalent. If delivery has already been taken, payment by the means or in the manner provided by the regulation discharges the buyer’s obligation unless the regulation is discriminatory, oppressive or predatory.
    • statuteORS 72.6160enactment date not established
      Show the words that state the rule
      Where the buyer receives notification of a material or indefinite delay or an allocation justified under ORS 72.6150 the buyer may by written notification to the seller as to any delivery concerned, and where the prospective deficiency substantially impairs the value of the whole contract under the provisions of ORS 72.6120 relating to breach of installment contracts, then also as to the whole: (a) Terminate and thereby discharge any unexecuted portion of the contract; or (b) Modify the contract by agreeing to take the available quota in substitution.
    • statuteORS 72.6160enactment date not established
      Show the words that state the rule
      If after receipt of such notification from the seller the buyer fails so to modify the contract within a reasonable time not exceeding 30 days the contract lapses with respect to any deliveries affected.
    • statuteORS 72.6160enactment date not established
      Show the words that state the rule
      The provisions of this section may not be negated by agreement except in so far as the seller has assumed a greater obligation under ORS 72.6150.
    • case193 Or 145Eggen v. WetterborgOr.decided 1951read it at the source ↗
      Show the words that state the rule
      According to the common law, a tenant remains liable for the agreed rent of demised premises so long as any part thereof remains in existence capable of being occupied or enjoyed by him, irrespective of injury or destruction by fire or other casualty.
    • case193 Or 145Eggen v. WetterborgOr.decided 1951read it at the source ↗
      Show the words that state the rule
      However, there are well-recognized exceptions to this rule. When parties enter into a contract on the assumption that some particular thing necessary to its *153 performance will continue to exist and be available for the purpose, and neither party agrees to be responsible for its continued existence and availability, the contract must be regarded as subject to the implied condition that, if before the time for performance, and without the default of either party, the particular thing ceases to exist or be available for the purpose, the contract shall be dissolved and the parties excused from performing it. This doctrine is known in this country as “supervening impossibility of performance.”
    • case193 Or 145Eggen v. WetterborgOr.decided 1951read it at the source ↗
      Show the words that state the rule
      In the light of the authorities hereinabove mentioned, as applied to the situation in the instant case, we find that the destruction of the buildings and service station equipment by the fire in question worked a termination of the original lease, and, of course, the sublease. Upon such termination the landlord was lawfully entitled to possession. Judgment reversed.
  19. read at the 2026-10-03 bar

    Will this force-majeure clause excuse our performance in Rhode Island?

    Nothing located answers that, and that is the finding: no Rhode Island force-majeure statute was found, and no Rhode Island decision construing a force-majeure CLAUSE. What Rhode Island does have is the common law behind the clause, and it is strict. Not one of the 32,579 sections of the Rhode Island General Laws carries a title for force majeure, impossibility, impracticability or frustration, so there is no Rhode Island force-majeure statute to apply; R.I. Gen. Laws § 6A-2-615, the UCC excuse for a seller of goods when a presupposed condition fails, is not among the Rhode Island statutes we publish, and exactly one Rhode Island opinion cites it - Iannuccillo v. Material Sand & Stone Corp., which cites it in support of the common-law doctrine and does not set its words out. Iannuccillo is also the only Rhode Island statement of IMPRACTICABILITY as such: "A party’s performance under a contract is rendered impracticable upon the occurrence of an event or a manifestation of a circumstance the nonoccurrence of which was a basic assumption on which the contract was made." Exactly ONE of the 26,773 published Rhode Island opinions uses the phrase 'force majeure' (Fuller Mill Realty, LLC v. Rhode Island Department of Revenue), and it only defines it in a footnote: "Force majeure has been defined as '[a]n event or effect that can be neither anticipated nor controlled; esp., an unexpected event that prevents someone from doing or completing something that he or she had agreed or officially planned to do.'" The Court then decided the case on the plain words of a waiver-of-hearing stipulation and never construed the clause. What Rhode Island does have is the common-law doctrines behind the clause. Frustration of purpose "excuse[s] a party from performing under a contract on the occurrence of an intervening or supervening condition that substantially frustrates the main purpose for which the parties entered into the contract", on a five-part test: "(1) the contract is partially executory, (2) a supervening event occurred after the contract was made, (3) the nonoccurrence of the event was a basic assumption on which the contract was made, (4) the occurrence frustrated the parties' principal purpose for the contract, (5) the frustration was substantial" (Tri-Town Construction Co. v. Commerce Park Associates 12, LLC). Impossibility is narrower still, and the one Rhode Island case that states it did not apply it: Lancaster v. Marshall agreed with "the well-established rule which the defendant invokes in this case, namely, that in contracts in which performance depends upon the continued existence of a certain person or thing, a condition is implied that the impossibility of performance arising from the perishing of the person or thing shall excuse the performance", then held "[b]ut that rule does not apply in the instant case because the evidence was conflicting", overruled all the defendant's exceptions and sent the case back for judgment on the verdict.

    The trap

    Three Rhode Island-specific hazards. First, the bar is destruction, not hardship: a party's obligation "will not be set aside merely because the performance under the contract becomes more difficult or expensive than originally anticipated", and the risk must be so severe that "the purpose underlying the contract must be totally and unforeseeably destroyed". Tri-Town rejected the 2008 financial collapse as a frustrating event for a developer's promissory note and affirmed summary judgment on the note and guaranty and the dismissal of the counterclaim, reversing only an attorney's-fee ruling. Second, the assumption has to be SHARED: Tri-Town holds that "for the doctrine of frustration of purpose to apply, both parties to the contract must share in the assumption that the particular purpose would not be frustrated", so a supplier's or lender's indifference to your purpose defeats the defence. Third, it is a shield only: "frustration of purpose — an affirmative defense against a breach of contract claim — is not a theory of liability in an affirmative cause of action", so a Rhode Island counterparty cannot sue to get its money back on that theory; Tri-Town affirmed dismissal of exactly that counterclaim. Because no Rhode Island opinion located construes a force-majeure clause, nothing here tells you how a Rhode Island court will read the words you draft, whether a catch-all sweeps in an unlisted event, whether notice is a condition, or whether the clause displaces these common-law doctrines.

    as of 2026-09-20

    12 authorities

    • caseNo. 2022-122-M.P.Fuller Mill Realty, LLC v. Rhode Island Department of Revenue Division of TaxationR.I.decided 2024
      Show the words that state the rule
      Force majeure has been defined as “[a]n event or effect that can be neither anticipated nor controlled; esp., an unexpected event that prevents someone from doing or completing something that he or she had agreed or officially planned to do.” Black’s Law Dictionary 788 (11th ed. 2019).
    • case139 A.3d 467Tri-Town Construction Co. v. Commerce Park Associates 12, LLCR.I.decided 2016read it at the source ↗
      Show the words that state the rule
      The main thrust behind that doctrine is to excuse a party from performing under a contract on the occurrence of an intervening or supervening condition that substantially frustrates the main purpose for which the parties entered into the contract in the first place.
    • case139 A.3d 467Tri-Town Construction Co. v. Commerce Park Associates 12, LLCR.I.decided 2016read it at the source ↗
      Show the words that state the rule
      To succeed on a theory of frustration based upon the occurrence of a supervening event, a party must show that: “(1) the contract is partially executory, (2) a supervening event occurred after the contract was made, (3) the nonoccurrence of the event was a basic assumption on which the contract was made, (4) the occurrence frustrated the parties’ principal purpose for the contract, (5) the frustration was substantial.” Iannuccillo v. Material Sand & Stone Corp., 713 A.2d 1234, 1238 (R.I. 1998).
    • case139 A.3d 467Tri-Town Construction Co. v. Commerce Park Associates 12, LLCR.I.decided 2016read it at the source ↗
      Show the words that state the rule
      In turn, that risk of increased difficulty or expense must be so severe that “the purpose underlying the contract must be totally and unforeseeably destroyed.” City of Warwick v. Boeng Corp., 472 A.2d 1214, 1219 (R.I. 1984)
    • case139 A.3d 467Tri-Town Construction Co. v. Commerce Park Associates 12, LLCR.I.decided 2016read it at the source ↗
      Show the words that state the rule
      frustration of purpose—an affirmative defense against a breach of contract claim—is not a theory of liability in an affirmative cause of action.
    • case34 A.2d 718Lancaster v. MarshallR.I.decided 1943read it at the source ↗
      Show the words that state the rule
      We agree with the well-established rule which the defendant invokes in this case, namely, that in contracts in which performance depends upon the continued existence of a certain person or thing, a condition is implied that the impossibility of performance arising from the perishing of the person or thing shall excuse the performance. Yerrington v. Greene, 7 R. I. 589. But that rule does not apply in the instant case because the evidence was conflicting
    • case139 A.3d 467Tri-Town Construction Co. v. Commerce Park Associates 12, LLCR.I.decided 2016read it at the source ↗
      Show the words that state the rule
      A party’s obligation under a contract “will not be set aside merely because the performance under the contract becomes more difficult or expensive than originally anticipated.”
    • case139 A.3d 467Tri-Town Construction Co. v. Commerce Park Associates 12, LLCR.I.decided 2016read it at the source ↗
      Show the words that state the rule
      As comment a. of § 265 makes clear, for the doctrine of frustration of purpose to apply, both parties to the contract must share in the assumption that the particular purpose would not be frustrated.
    • case34 A.2d 718Lancaster v. MarshallR.I.decided 1943read it at the source ↗
      Show the words that state the rule
      All of defendant’s exceptions are overruled and the case is remitted to the superior court for the entry of judgment on the verdict.
    • case139 A.3d 467Tri-Town Construction Co. v. Commerce Park Associates 12, LLCR.I.decided 2016read it at the source ↗
      Show the words that state the rule
      we affirm in part and vacate in part the judgment of the Superior Court. We affirm the Superior Court’s decision to grant summary judgment in favor of the plaintiff on claims of the breach of promissory note and breach of guaranty, as well as its dismissal of CPA’s counterclaim.
    • caseNo. 2022-122-M.P.Fuller Mill Realty, LLC v. Rhode Island Department of Revenue Division of TaxationR.I.decided 2024
      Show the words that state the rule
      V Conclusion For the reasons set forth in this opinion, we quash the order of the District Court denying the Division’s motion to dismiss, and we remand the case to the District Court with directions that it enter an order dismissing the case.
    • case713 A.2d 1234Iannuccillo v. Material Sand & Stone Corp.R.I.decided 1998read it at the source ↗
      Show the words that state the rule
      A party’s performance under a contract is rendered impracticable upon the occurrence of an event or a manifestation of a circumstance the nonoccurrence of which was a basic assumption on which the contract was made. See 2 Restatement (Second) Contracts § 261 (1981); see, e.g., G.L.1956 § 6A-2-615; 18 Samuel Williston, Contracts § 1963 (3d ed.1978)
  20. read at the 2026-10-03 bar

    Without a force majeure clause, will Utah excuse performance because of an event that made it impracticable?

    Only narrowly. The doctrine excuses performance if an unforeseen event occurs after formation of the contract and without fault of the obligated party, and that event makes performance of the obligation impossible or highly impracticable. In Central Utah Water Conservancy District v. Upper East Union Irrigation Co. the Utah Supreme Court held that a party is not excused for impracticability when the event leading to the impracticability was known to the parties before contracting, and held the failure to perform there not excused for independent reasons: the event was not unforeseen, the party did not show performance was impracticable because it did not even attempt to obtain the required permits, and it had assumed the risk of failing to obtain them.

    The trap

    A party that knew of the risk when it signed, or that took on the job of obtaining approvals, cannot later call that risk impracticability; it has to allocate it in the contract. The doctrine also requires an attempt to perform: failing even to try to obtain permits defeated the defense. The attempt has to be a good faith one, and the court said that had the party sought the permits and been denied, it might have had a colorable claim.

    as of 2026-09-17

    6 authorities

    • case2013 UT 67Central Utah Water Conservancy District v. Upper East Union Irrigation Co.Utahdecided 2013read it at the source ↗
      Show the words that state the rule
      A party is not excused for impracticability, however, when the event leading to the impracticability was known to the parties prior to contracting.
    • case2013 UT 67Central Utah Water Conservancy District v. Upper East Union Irrigation Co.Utahdecided 2013read it at the source ↗
      Show the words that state the rule
      We hold that CUWCD's failure to perform is not excused by the doctrine of impracticability for several independent reasons. First, CUWCD cannot establish that the event giving rise to the claim of impracticability was unforeseen. Second, CUWCD failed to show that performance was impracticable because it did not even attempt to obtain the required permits. Finally, even had it attempted to do so, CUWCD assumed the risk of failing to obtain the requisite permits.
    • case2013 UT 67Central Utah Water Conservancy District v. Upper East Union Irrigation Co.Utahdecided 2013read it at the source ↗
      Show the words that state the rule
      Additionally, a party may not defend on grounds of impracticability when that party takes on the risk that a supervening event will occur and render performance impracticable or impossible.
    • case2013 UT 67Central Utah Water Conservancy District v. Upper East Union Irrigation Co.Utahdecided 2013read it at the source ↗
      Show the words that state the rule
      Section 7 of the Agreement, entitled "Permits for Construction," states that "CUWCD and/or its contractor shall obtain all construction permits required by all local jurisdictions and any Stream Alteration/ § 404 permits required for the reconstruction of the TCC diversion." (Emphasis added). CUWCD thus affirmatively contracted to obtain all necessary permits and assumed the risk that such permits may be difficult, or even impossible, to obtain. See Kilgore Pavement Maint., LLC v. W. Jordan City, 2011 UT App 165, ¶¶ 7-8 , 257 P.3d 460 (holding that where a party agreed that it "shall furnish and assume full responsibility for all materials," it implicitly assumed the risk that the materials may have been more expensive or more difficult to obtain than originally anticipated (emphasis added)). While CUWCD explicitly undertook the obligation of obtaining the necessary permits, its performance under the Agreement was not contingent on its ability to do so.
    • case2013 UT 67Central Utah Water Conservancy District v. Upper East Union Irrigation Co.Utahdecided 2013read it at the source ↗
      Show the words that state the rule
      The doctrine of impracticability exeuses a party's performance "if an unforeseen event occurs after formation of the contract and without fault of the obligated party, which event makes performance of the obligation impossible or highly impracticable." W. Props. v. S. Utah Aviation, Inc., 776 P.2d 656, 658 (Utah Ct.App.1989) (footnotes omitted)
    • case2013 UT 67Central Utah Water Conservancy District v. Upper East Union Irrigation Co.Utahdecided 2013read it at the source ↗
      Show the words that state the rule
      Additionally, there is no dispute that CUWCD has not yet applied for or otherwise sought to obtain the permits necessary to undertake the replacement of the TCC Diversion. While CUWCD's replacement of the TCC Diversion may be "inconsistent with evolving LPRDS objectives," without a good faith attempt to obtain the necessary permits, CUWCD cannot establish that performance is impracticable. Thus, even assuming that CUWCD did not know of the LPRDS Project prior to execution of the Agreement, had CUWCD sought to obtain permits and been denied, it might have a colorable claim for impracticability. - But here, where CUWCD has not even attempted to obtain the necessary permits, it cannot reasonably make such a claim.
  21. read at the 2026-10-03 bar

    Will our force-majeure clause, or the doctrine behind it, excuse performance in Virginia?

    The doctrine will, on narrow terms: in RECP IV the county's removal of the cap on floor area ratio was such a change, and the Supreme Court of Virginia held that the circuit court was correct to sustain the impossibility defence on it, and the clause will only if the event is genuinely outside your control. Restating Hampton Roads Bankshares, the Supreme Court of Virginia said in RECP IV: "The defense of impossibility of performance is an established principle of contract law. In Virginia, it is 'well settled that where impossibility is due . . . to the fortuitous destruction or change in the character of something to which the contract related, or which by the terms of the contract was made a necessary means of performance, the promisor will be excused, unless he either expressly agreed in the contract to assume the risk of performance, whether possible or not, or the impossibility was due to his fault.'" On the clause itself, Gordonsville Energy is the only Virginia decision located that actually litigates whether an event qualified: the contract's force-majeure article required circumstances beyond the claiming party's reasonable control, the generator rotor had been designed and built by General Electric, and the Court upheld an instruction that "Although Gordonsville Energy relied on General Electric Company to design and construct the rotor, Gordonsville Energy is responsible to Virginia Power for General Electric's performance of those activities just as if Gordonsville Energy had performed them itself". The jury then found the outage was not a force majeure event.

    The trap

    Gordonsville is the trap in one case: a clause excusing only what is "beyond [Gordonsville's] reasonable control", as the opinion renders the contract's words, does not put your subcontractor's or supplier's performance beyond your control, and the negligence of the firm you engaged is imputed to you. The doctrinal limits cut the same way: the excuse is unavailable where the promisor expressly assumed the risk, which is exactly what a carefully drafted allocation clause does, and where the impossibility was due to his own fault.

    as of 2026-09-20

    9 authorities

    • case295 Va. 268RECP IV WG Land Investors LLC v. Capital One Bank (USA), N.A.Va.decided 2018read it at the source ↗
      Show the words that state the rule
      The defense of impossibility of performance is an established principle of contract law. In Virginia, it is “well settled that where impossibility is due . . . to the fortuitous destruction or change in the character of something to which the contract related, or which by the terms of the contract was made a necessary means of performance, the promisor will be excused, unless he either expressly agreed in the contract to assume the risk of performance, whether possible or not, or the impossibility was due to his fault.”
    • case257 Va. 344Gordonsville Energy, L.P. v. Virginia Electric & Power Co.Va.decided 1999read it at the source ↗
      Show the words that state the rule
      Over Gordonsville's objection, the trial court gave the jury Instruction No. 10, which stated: Gordonsville Energy is responsible to Virginia Power under the parties' contract for the design and construction of Gordonsville Energy's electric generating facility, including the steam turbine generator, its rotor and the rotor's component parts that failed in September, 1995. Although Gordonsville Energy relied on General Electric Company to design and construct the rotor, Gordonsville Energy is responsible to Virginia Power for General Electric's performance of those activities just as if Gordonsville Energy had performed them itself.
    • case257 Va. 344Gordonsville Energy, L.P. v. Virginia Electric & Power Co.decided 1999read it at the source ↗
      Show the words that state the rule
      In a later section of the Contract, § 14.1, the parties agreed that an outage would be excused if it was "due solely to circumstances beyond [Gordonsville's] reasonable control . . . including . . . damage to or breakdown of power generation materials and equipment that is not caused by normal wear and tear."
    • case257 Va. 344Gordonsville Energy, L.P. v. Virginia Electric & Power Co.decided 1999read it at the source ↗
      Show the words that state the rule
      Thus, under the Contract, Gordonsville remained responsible for the contractual obligations it subcontracted to General Electric and was excused from performance only if an outage also was "beyond 12 the reasonable control" of any subcontractors hired to perform Gordonsville's duties set forth in § 8.2.
    • case257 Va. 344Gordonsville Energy, L.P. v. Virginia Electric & Power Co.decided 1999read it at the source ↗
      Show the words that state the rule
      The jury returned its verdict in favor of Virginia Power, finding that "the [September 1995] outage was not a force majeure event."
    • case295 Va. 268RECP IV WG Land Investors LLC v. Capital One Bank (USA), N.A.Va.decided 2018read it at the source ↗
      Show the words that state the rule
      The County’s removal of the cap on FAR presented such a change relative to the performance of the FAR formula. Thus, the circuit court was also correct in sustaining Capital One’s impossibility defense, as asserted in its Plea in Bar and Motion for Summary Judgment, to WG Land’s claims that Capital One breached the FAR formula.
    • case295 Va. 268RECP IV WG Land Investors LLC v. Capital One Bank (USA), N.A.Va.decided 2018read it at the source ↗
      Show the words that state the rule
      It cannot be said that Capital One was at “fault” for the legislative action taken by the County’s governing board. “Fault” in the context of the 23 impossibility doctrine implies the violation of a tort or contract duty, which WG Land has failed to either allege or establish with regard to Capital One’s lobbying efforts.
    • case257 Va. 344Gordonsville Energy, L.P. v. Virginia Electric & Power Co.Va.decided 1999read it at the source ↗
      Show the words that state the rule
      In granting Instruction No. 10, the trial court ruled that the Contract did not excuse Gordonsville's failure to perform under the Contract if the failure was caused by the negligence of a subcontractor retained by Gordonsville to perform functions for which Gordonsville was responsible. Under familiar principles of contract interpretation, we reach the same conclusion and hold that the trial court did not err in granting Instruction No. 10.
    • case257 Va. 344Gordonsville Energy, L.P. v. Virginia Electric & Power Co.Va.decided 1999read it at the source ↗
      Show the words that state the rule
      For these reasons, we will affirm the trial court's judgment in favor of Virginia Power on Counts I and V. We will also reverse the trial court's judgment on Count II and enter final judgment in favor of Gordonsville on that Count. Affirmed in part, reversed in part, and final judgment.
  22. read at the 2026-10-03 bar

    Can our counterparty stop performing because the deal's purpose was destroyed by an outside event?

    Rarely. Wisconsin defines the frustration defence, tracking Restatement (Second) of Contracts § 265, as requiring that (1) the party's principal purpose in making the contract is frustrated; (2) without that party's fault; (3) by the occurrence of an event, the non-occurrence of which was a basic assumption on which the contract was made (Convenience Store Leasing, quoting Ryan v. Sheppard). The Court of Appeals recorded that the doctrine is given a narrow construction and applied sparingly, because it renders null the explicit terms of the contract and is counter to the strong impulse in the law to enforce contracts as written, and that the party asserting the defence bears the burden of proving it.

    The trap

    Foreseeability and allocated risk defeat the defence before the elements are reached: the court recorded that the doctrine does not apply where the risk of the supervening event was reasonably foreseeable and could and should have been anticipated by the parties and provision made for it in the agreement. The Supreme Court of Wisconsin has put the same point as a rule of contract allocation: if the parties have contracted with reference to the frustrating event or have contemplated the risks arising from it, they may not invoke the doctrine of frustration, and a cost that is merely unwanted or higher than expected is not the same as one whose non-occurrence the deal was built on. And 'frustrated' does not mean unprofitable: the Restatement illustration the court quoted has a gas-station lessee who can still operate at a substantial loss, whose principal purpose is therefore not substantially frustrated and who remains liable for rent, with the same result where the loss is caused by a government regulation or the termination of the supply franchise. The frustrating event must strike at the foundation of the contract so that performance would be virtually worthless and meaningless.

    as of 2026-09-17

    9 authorities

    • case2019 WI App 40Convenience Store Leasing and Management v. Annapurna MarketingWis. Ct. App.decided 2019read it at the source ↗
      Show the words that state the rule
      our cases define the elements of this defense as follows: “(1) the party’s principal purposes in making the contract is frustrated; (2) without that party’s fault; (3) by the occurrence of an event, the non-occurrence of which was a basic assumption on which the contract was made.”
    • case2019 WI App 40Convenience Store Leasing and Management v. Annapurna MarketingWis. Ct. App.decided 2019read it at the source ↗
      Show the words that state the rule
      The doctrine of frustration is “given a narrow construction” and “applied sparingly.” 17A AM. JUR. 2D Contracts § 641 (2016). This is so because it renders null the explicit terms of the contract and is counter to the strong impulse in the law to enforce contracts as written.
    • case2019 WI App 40Convenience Store Leasing and Management v. Annapurna MarketingWis. Ct. App.decided 2019read it at the source ↗
      Show the words that state the rule
      “The doctrine does not apply where the risk of the event that has supervened to cause the alleged 9 No. 2017AP1505 frustration was reasonably foreseeable and could and should have been anticipated by the parties and provision made for it in the agreement.”
    • case2019 WI App 40Convenience Store Leasing and Management v. Annapurna MarketingWis. Ct. App.decided 2019read it at the source ↗
      Show the words that state the rule
      The party asserting the defense has the burden to prove frustration of purpose.
    • case2019 WI App 40Convenience Store Leasing and Management v. Annapurna MarketingWis. Ct. App.decided 2019read it at the source ↗
      Show the words that state the rule
      The Restatement affirms that frustration is not substantial merely because “the transaction has become less profitable for the affected party or even that he will sustain a loss.” Id. An example from the Restatement is helpful and especially pertinent here: A leases a gasoline station to B. A change in traffic regulations so reduces B’s business that he is unable to operate the station except at a substantial loss. B refuses to make further payments of rent. If B can still operate the station, even though at such a loss, his principal purpose of operating a gasoline station is not substantially frustrated. B’s duty to pay rent is not discharged, and B is liable to A for breach of contract. The result would be the same if substantial loss were caused instead by a government regulation rationing gasoline or a termination of the franchise under which B obtained gasoline.
    • case2019 WI App 40Convenience Store Leasing and Management v. Annapurna MarketingWis. Ct. App.decided 2019read it at the source ↗
      Show the words that state the rule
      Moreover, the frustrating event must strike at the foundation of the contract—a basic assumption on which the contract was made such that the party’s performance, due to this unexpected circumstance, would be “virtually worthless” and “meaningless.”
    • case2019 WI App 40Convenience Store Leasing and Management v. Annapurna MarketingWis. Ct. App.decided 2019read it at the source ↗
      Show the words that state the rule
      As our supreme court stated in Chicago, Milwaukee, “if the parties have contracted with reference [to the frustrating event] or have contemplated the risks arising from it, they may not invoke the doctrine of frustration.” Chicago, Milwaukee, 82 Wis. 2d at 527.
    • case2019 WI App 40Convenience Store Leasing and Management v. Annapurna MarketingWis. Ct. App.decided 2019read it at the source ↗
      Show the words that state the rule
      In short, the Defendants have not met their burden to prove that the principal purpose of the FSA was frustrated due to U.S. Oil’s demand for alterations to the bathrooms, nor that this demand was contrary to a basic assumption underlying the FSA.
    • case2019 WI App 40Convenience Store Leasing and Management v. Annapurna MarketingWis. Ct. App.decided 2019read it at the source ↗
      Show the words that state the rule
      We conclude AP Marketing is not excused from performance of the FSA under the frustration of purpose doctrine. The circuit court erroneously dismissed the claim on this ground. We remand the case to the circuit court with instructions to reinstate Bulk’s claim that AP Marketing breached the FSA. Because the circuit court did not determine whether AP Marketing breached the FSA, that issue—along with any other issues of contractual interpretation and performance, including the stipulated damages provision—remains to be adjudicated. By the Court.—Judgment reversed and cause remanded with directions.